Section 1. Summary
Title of project
Yakima Hatchery - Final Design
BPA project number 9006900
Short description
Develop the final design and construction services of Yakima River spring chinook central outplanting facility at Cle Elum, WA, and preliminary design for three satellite acclimation facilities.
Business name of agency, institution or organization requesting funding
CH2M Hill
Proposal contact person or principal investigator
|
Section 2. Goals
General
Target stock | Life stage | Mgmt code (see below) |
Upper Yakima River Spring Chinook | All fresh water life stages | S |
Section 3. Background
Stream area affected
Stream name Yakima River
Stream miles affected All
Land ownership Bonneville Power Administration
Acres affected 500
History
Project was started in 1990 to provide technical design services for Yakima Fisheries Project.
Biological results achieved
This is an engineering project.
Project reports and papers
Project provides design drawings and design specifications for Yakima Fisheries Project spring chinook propagation facilities.
Adaptive management implications
N/A
Section 4. Purpose and methods
Specific measureable objectives
N/A
Critical uncertainties
N/A
Biological need
Project is needed to provide technical design services for Project 88-115 (Yakima Hatchery Construction).
Hypothesis to be tested
N/A
Section 5. Planned activities
Project completion date 1998Section 6. Outcomes, monitoring and evaluation
SUMMARY OF EXPECTED OUTCOMES
Expected performance of target population or quality change in land area affected
Engineering drawings, specifications, and design services during hatchery construction have been, and will be, provided to BPA.
Contribution toward long-term goal
Upper Yakama Basin spring chinook
Environmental attributes affected by the project
N\A
Changes assumed or expected for affected environmental attributes
N\A
Measure of attribute changes
N\A
Coordination outcomes
FY 95: 80% final design for Cle Elum Hatchey completed and reviewed.
MONITORING APPROACH
N/A
Section 7. Relationships
Related BPA project | Relationship |
8811500 Hatchery construction | |
8812000 Project planning, coordination, management, research, and monitoring and evaluation | |
9506200 Project planning, coordination, management, research, and monitoring and evaluation | |
9506300 Project planning, coordination, management, research, and monitoring and evaluation | |
9506400 Project planning, coordination, management, research, and monitoring and evaluation |
Opportunities for cooperation
N/A
Section 8. Costs and FTE
1997 Planned $900,000
Future funding needs | Past obligations (incl. 1997 if done) | |||||||||||||||||||||||||||||||||||||||||||||||||
|
|