FY 2001 Innovative proposal 22032

Additional documents

TitleType
22032 Narrative Narrative

Section 1. Administrative

Proposal titleDevelop a practical method through diet modification to improve quality of hatchery reared steelhead trout and coho salmon.
Proposal ID22032
OrganizationU.S. Fish & Wildlife Service (USFWS)
Proposal contact person or principal investigator
NameFrederic T. Barrows
Mailing address4050 Bridger Canyon Road Bozeman, Montana
Phone / email4065879265 / [email protected]
Manager authorizing this projectFrederic T. Barrows
Review cycleFY 2001 Innovative
Province / SubbasinSystemwide / Systemwide
Short descriptionPrevent fin erosion in steelhead and sunburn (steatitis) in coho salmon by providing cost-effective, nutritionally complete, feeds. Current feeds are deficient in essential trace elements.
Target speciessteelhead trout and coho salmon
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2001 cost
Personnel FTE: 3 full time GS-5, 1 year $70,989
Fringe $14,198
Supplies Feed ingredients, analytical supplies/services, etc. $69,903
Travel PI visits to study locations, lab and production $9,340
Indirect @27% $65,070
Capital experimental tanks and feeders for installation at a production Coho hatchery $11,500
PIT tags $0
Subcontractor $0
$241,000
Total estimated budget
Total FY 2001 cost$241,000
Total FY 2001 budget request$241,000
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
USFWS, Bozeman FTC PI time, support staff, water costs $27,481 in-kind
University of Idaho PI time, support staff $23,000 in-kind
USFWS, Abernathy FTC PI time $19,741 in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Not Innovative
Date:
Dec 15, 2000

Comment:

While the panel recognizes that fin erosion and sunburn are fish production problems, this proposal was not viewed as being sufficiently innovative because diet modification is standard hatchery practice. The Panel would have been more supportive if the proposal had established priority need for the work relative to Fish and Wildlife Program priorities. Idaho State University was incorrectly identified as a project co-sponsor.
Recommendation:
Do Not Fund
Date:
Jan 17, 2001

Comment:

Agree with ISRP comments.
Recommendation:
Do Not Fund
Date:
Jan 17, 2001

Comment:

Agree with ISRP comments.