FY 2002 Mountain Snake proposal 200206700
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
28040 Narrative | Narrative |
Mountain Snake: Salmon Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Mountain Snake: Salmon Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Section 1. Administrative
Proposal title | Holistic Restoration of Critical Habitat on Non-federal Lands, Upper Salmon Watershed, Idaho |
Proposal ID | 200206700 |
Organization | Custer Soil & Water Conservation District / Idaho Governor's Office of Species Conservation (Custer SWCD / OSC) |
Proposal contact person or principal investigator | |
Name | Karma Bragg, Custer SWCD |
Mailing address | P.O. Box 305 Challis, ID 83226 |
Phone / email | 2088794428 / [email protected] |
Manager authorizing this project | Ted O'Neal |
Review cycle | Mountain Snake |
Province / Subbasin | Mountain Snake / Salmon |
Short description | Collaborative effort to implement projects on non-federal lands that are effective at improving habitat conditions (and survival rates) for native anadromous and resident salmonids in the Upper Salmon watershed, Idaho. |
Target species | Snake River Spring/Summer Chinook, Snake River Steelhead, Bull Trout, Westslope Cutthroat Trout, Redband Rainbow Trout, and Other Aquatic and Riparian-associated Species Native to the Watershed. |
Project location
Latitude | Longitude | Description |
---|---|---|
44.26 | -114.37 | Upper Salmon Watershed HUC No. 17060201 |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Habitat RPA Action 149 |
Habitat RPA Action 150 |
Habitat RPA Action 151 |
Habitat RPA Action 153 |
RM&E RPA Action 183 |
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|---|---|---|
NMFS | Action 149 | NMFS | BOR shall initiate programs in three priority subbasins (identified in the Basinwide Recovery Strategy) per year over 5 years, in coordination with NMFS, FWS, the states and others, to address all flow, passage, and screening problems in each subbasin over 10 years. The Corps shall implement demonstration projects to improve habitat in subbasins where water-diversion-related problems could cause take of listed species. Under the NWPPC program, BPA addresses passage, screening, and flow problems, where they are not the responsibility of others. BPA expects to expand on these measures in coordination with the NWPPC process to complement BOR actions described in the action above. |
NMFS | Action 150 | NMFS | In subbasins with listed salmon and steelhead, BPA shall fund protection of currently productive non-Federal habitat, especially if at risk of being degraded, in accordance with criteria and priorities BPA and NMFS will develop by June 1, 2001. |
NMFS | Action 154 | NMFS | BPA shall work with the NWPPC to ensure development and updating of subbasin assessments and plans; match state and local funding for coordinated development of watershed assessments and plans; and help fund technical support for subbasin and watershed plan implementation from 2001 to 2006. Planning for priority subbasins should be completed by the 2003 check-in. The action agencies will work with other Federal agencies to ensure that subbasin and watershed assessments and plans are coordinated across non-Federal and Federal land ownerships and programs. |
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
2000 | S-28 (Gini Canal) Consolidation -- Eliminated the S-29 water diversion along the mainstem by converting irrigators from flood to sprinkler irrigation. The S-26 diversion was also closed. |
1997 | Constructed 0.8 miles of enhancement fence and 8 barbs to stop bank erosion on private land along 0.2 miles of the mainstem Salmon River. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
199202603 | Upper Salmon Basin Watershed Project (USBWP) Administration/Implementation Support | Administrative and public outreach functions associated with the actual habitat restoration planning and work (RPA Action #149, 150, 151, 152, 153, and 154) described in this proposal. |
199306200 | Salmon River Anadromous Fish Passage Enhancement | RPA Action # 149, 150, 151, 152, 153, 154 - Improve Passage on Lemhi, Pahsimeroi, and East Fork watersheds. |
199600700 | Upper Salmon River Diversion Consolidation Project | RPA Action # 149, 150, 151, 152, 153, 154 - Consolidate irrigation diversions on Lemhi, Pahsimeroi, and Upper Salmon watersheds. |
199401500 | Idaho Fish Screen Improvements (IDFG) | RPA Action # 149, 150, 151, 152, 153, 154 - Construction and installation of fish screens and diversions on Lemhi, Pahsimeroi, East Fork and Upper Salmon watersheds. |
199107300 | Idaho Natural Production M&E (IDFG) | RPA Action # 182 - Annual monitoring of salmonid abundance at established stations. |
198909803 | Idaho Supplementation Studies (IDFG, ShoBan Tribes, UI, USFWS) | Relationship to be developed. |
199906300 | Aquatic Ecosystem Review for the Upper Salmon Subbasin (UI/ERG) | RPA Action # 152, 154 - Environmental evaluations and analyses supporting selected USBWP restoration work. |
199405000 | Upper Salmon River Habitat Improvement and M&E (ShoBan Tribes) | RPA Action # 149, 150, 152, 183 - Habitat improvement and associated monitoring. |
199705700 | Upper Salmon River Production Program (ShoBan Tribes) | Relationship to be developed. |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Characterize existing conditions and trends within the watershed, and identify data gaps. | a. Compile available physical and biological information into a common, web-accessible database maintained by a state agency to be identified in early 2002. | 1 | $30,483 | Yes |
1. | b. Prepare a written report to summarize existing information on habitat conditions within the watershed and on the status of natural processes affecting the formation, maintenance, and quality of this habitat. | 1 | $6,547 | Yes |
1. | c. Summarize existing data on biological conditions within the watershed, in the same written report. | 1 | $2,872 | Yes |
1. | d. Identify data gaps and outline an approach to filling them, in the same written report. | 1 | $5,808 | Yes |
2. Use available predictive or other tools (including EDT and others) to build on existing knowledge, to refine habitat strategies, and to help prioritize restoration opportunities on non-federal lands in the watershed. | a. USBWP Technical Team and others will use the results of tasks 1a-d and EDT and/or other appropriate models to predict habitat trends, future conditions, and the relative benefits of varied habitat strategies and measures. | Ongoing | $577,008 | Yes |
2. | b. USBWP Advisory Committee will work collaboratively with the Technical Team to prioritize available restoration opportunities in a way consistent with the Basinwide Salmon Recovery Strategy. | Ongoing | $2,658 | |
3. Complete project designs for selected restoration opportunities. | a. Use Mike-11 and/or other physical models where appropriate to predict future conditions and refine conceptual project designs. | Ongoing | $572,497 | Yes |
3. | b. Complete preliminary engineering and design work for projects. | Ongoing | $70,719 | Yes |
3. | c. USBWP Biologist will contribute information the Environmental Compliance Specialist (funded under BPA Contract 1992-026-03) needs to complete written biological assessments. | Ongoing | $7,908 | |
3. | d. USBWP Biologist will assist the Environmental Compliance Specialist in conducting environmental surveys and completing associated documents (NEPA, HAZMAT). | Ongoing | $7,908 | |
3. | e. USBWP Biologist will help a cultural resources specialist assess potential project impacts and assure design adjustments where appropriate. | Ongoing | $7,908 | |
3. | f. Prepare final design packages. | Ongoing | $36,715 | Yes |
3. | g. USBWP Biologist will assist the Environmental Compliance Specialist in obtaining needed permits. | Ongoing | $2,658 | |
3 | h. USBWP Biologist and Engineer will help the Environmental Compliance Specialist assemble information needed to procure appraisals for acquisition of fee titles or easements. | Ongoing | $11,373 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Use available predictive or other tools (including EDT and others) to build on existing knowledge, to refine habitat strategies, and to help prioritize restoration opportunities on non-federal lands in the watershed. | 2003 | 2006 | $2,553,000 |
2. Complete first full cycle of subbasin planning (to include an assessment and development of a subbasin plan) for the Upper Salmon watershed. | 2003 | 2004 | $23,000 |
3. Prioritize habitat actions (projects) based on predictive tools, and the subbasin assessment and plan for the Upper Salmon watershed. | 2003 | 2006 | $28,000 |
4. Work with NMFS in development of the recovery plan to establish population and ESU goals for abundance, productivity, distribution, and diversity of ESA listed fish. | 2003 | 2004 | $14,000 |
5. Continue to complete project designs for selected restoration opportunities. | 2003 | 2006 | $3,084,000 |
Outyear budgets for Planning and Design phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$1,369,000 | $1,411,000 | $1,438,000 | $1,484,000 |
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Minimize losses and migratory delays or blockages of salmonids that are associated with irrigation diversion structures and water withdrawals along streams on non-federal lands. | a. Work cooperatively with irrigators, NRCS, BOR, IDFG, the Shoshone-Bannock Tribes, and others to construct diversion and fish screening structures that have reduced impacts on fish. | Ongoing | $12,950 | Yes |
1. | b. Work with willing landowners to secure instream flows through the purchase, lease, exchange, or seasonal rental of water rights along critical spawning/rearing habitats or migratory corridors for ESA-listed salmonids. | Ongoing | $37,504 | |
1. | c. Restore habitat connectivity by working with landowners to increase flows in dewatered stream reaches that would otherwise be used by fluvial or anadromous salmonids. | Ongoing | $244,791 | Yes |
1. | d. Work with IDFG, BLM, USFS, BOR, and the Shoshone-Bannock Tribes to address critical water diversions and fish barriers. | Ongoing | $55,103 | Yes |
1. | e. Work cooperatively with irrigators, IDFG, and BOR to consolidate irrigation diversions where such actions are feasible and will reduce fish migration delays. | Ongoing | $286,944 | Yes |
2. Improve critical habitats and survival rates for salmonids on non-federal lands by improving riparian conditions and reducing streambed sedimentation and water temperatures. | a. Work with landowners to implement grazing control measures (fenced riparian exclosures, conservation easements, and/or new management practices) along critical habitat occupied by listed salmonids | Ongoing | $186,831 | Yes |
2. | b. Plant native riparian vegetation in areas slow to respond to other management changes. | Ongoing | $55,103 | Yes |
2. | c. Work cooperatively with NRCS, IDEQ, ISCC, and others to implement improved feedlot practices, including relocations away from stream channels. | Ongoing | $81,448 | Yes |
2. | d. Develop off-stream watering for livestock, to allow recovery of sensitive riparian/wetland habitats. | Ongoing | $0 | Yes |
2. | e. Restore floodplain function and habitat complexity where habitats have been simplified along critical reaches. | Ongoing | $0 | Yes |
2. | f. Acquire easements and fee titles from willing landowners, for long-term habitat protection. | Ongoing | $12,950 | |
3. Oversee contractors during construction projects. | a. Conduct ongoing engineering inspections. | Ongoing | $5,197 | |
3. | b. Complete final engineering inspection and sign off on completed work. | Ongoing | $5,197 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Minimize losses and migratory delays or blockages of salmonids that are associated with irrigation diversion structures and water withdrawals along streams on non-federal lands. | 2003 | 2006 | $2,740,000 |
2. Improve critical habitats and survival rates for salmonids on non-federal lands by improving riparian conditions and reducing streambed sedimentation and water temperatures. | 2003 | 2006 | $1,456,000 |
3. Oversee contractors during construction projects. | 2003 | 2006 | $21,000 |
Outyear budgets for Construction and Implementation phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$1,008,500 | $1,039,000 | $1,068,500 | $1,101,000 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Use an adaptive management approach to protect investments directed toward habitat restoration and to ensure that restoration objectives are achieved. | a. Review annual M&E results (see Task 3a) and identify necessary actions. | Ongoing | $7,326 | Yes |
1. | b. Modify project approaches and/or design criteria as needed to improve effectiveness. | Ongoing | $7,326 | Yes |
1. | c. Implement design modifications (e.g., revegetation, structural modifications, or other adjustments). | Ongoing | $130,260 | Yes |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Use an adaptive management approach to protect investments directed toward habitat restoration and to ensure that restoration objectives are achieved. | 2003 | 2006 | $640,000 |
Outyear budgets for Operations and Maintenance phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$152,000 | $157,000 | $163,000 | $168,000 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Refine the USBWP's monitoring program. | a. Refine performance metrics and criteria for USBWP projects and programs. | 1 | $4,848 | Yes |
1. | b. Identify needs for monitoring data that are being met by existing USBWP programs or that could be met by these programs or the ongoing programs of other entities. | 1 | $5,373 | Yes |
1. | c. Identify unmet monitoring needs. | 1 | $3,273 | Yes |
1. | d. Develop a comprehensive plan for monitoring the performance of the USBWP's projects and overall program, capitalizing on previous investments in data collection efforts to the greatest degree possible. | 1 | $14,823 | Yes |
2. Implement the monitoring program. | a. Conduct implementation (compliance) monitoring. Work with landowners/operators to ensure implementation, operation, and maintenance of projects is according to design. Modify contracts as warranted. | Ongoing | $2,828 | Yes |
2. | b. Conduct effectiveness monitoring. Gather and summarize data needed to monitor and evaluate the physical, biological, and cost-effectiveness of USBWP restoration projects. | Ongoing | $36,935 | Yes |
3. Evaluate monitoring data to allow adaptive management of the USBWP program. | a. Evaluate monitoring data annually and recommend appropriate refinements to USBWP predictive tools, restoration priorities, and programs. Summarize these evaluations and resultant recommendations in a written report every year. | Ongoing | $25,274 | Yes |
3. | b. Present the annual monitoring report to the public and post on website. | Ongoing | $2,199 | Yes |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Implement the monitoring program. | 2003 | 2006 | $174,000 |
2. Evaluate monitoring data to allow adaptive management of the USBWP program. | 2003 | 2006 | $123,000 |
Outyear budgets for Monitoring and Evaluation phase
FY 2005 | FY 2003 | FY 2004 | FY 2006 |
---|---|---|---|
$75,000 | $70,000 | $73,000 | $79,000 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2002 cost |
---|---|---|
Personnel | FTE: 1.00 Biologist @ $43,139/yr, 0.25 Engineer @ $47,174/yr, 0.33 Office Manager @$20,800/yr | $61,797 |
Fringe | 36.9% | $22,803 |
Supplies | Computer, office suplies, field equipment, etc. | $10,000 |
Travel | Vehicle lease, insurance, per diem, etc. | $13,500 |
Indirect | 5.0% (applied to all cost elements) | $122,264 |
Capital | $1,003,981 | |
NEPA | $20,000 | |
Subcontractor | Univ. Idaho/ERG (Faculty @ $60,800/yr; Grad student @ $35,900/yr; Direct expenses @ $34,500/yr) | $132,200 |
Subcontractor | Clearwater BioStudies, Inc. (C. Huntington and staff @ $27,500/yr; Direct expenses @ $4,500/yr) | $32,000 |
Subcontractor | Engineering and design firm | $95,250 |
Subcontractor | LiDAR, survey, and map preparation contractor | $1,050,000 |
Other | Staff training | $3,750 |
$2,567,545 |
Total estimated budget
Total FY 2002 cost | $2,567,545 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2002 budget request | $2,567,545 |
FY 2002 forecast from 2001 | $0 |
% change from forecast | 0.0% |
Reason for change in estimated budget
The USBWP program is being reconfigured on a geographic basis in order to address past ISRP comments and new federal agency plans. In FY 02 the USBWP will be restructured consistent with a geographic approach for project selection, planning, implementation, and monitoring. The following ongoing projects will be restructured into this approach: Idaho Upper Salmon Basin Watershed Habitat Projects, No. 199401700 Salmon River Anadromous Fish Passage Enhancement, No. 199306200 Upper Salmon River Diversion Consolidation Project, No. 199600700
Reason for change in scope
Program is being restructured to make adaptive management more explicit and for consistency with past ISRP comments and new federal agency plans.
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|---|---|---|
Univ. Idaho/Ecohydraulics Res. Group | Use of surveying equipment and computer costs | $10,000 | in-kind |
NRCS | Technical and engineering assistance | $0 | in-kind |
BOR | Technical and engineering assistance | $0 | in-kind |
IDFG | Fisheries Biologists (Tech Team members) | $1,000 | in-kind |
BLM | Fisheries Biologist (Tech. Team member) | $500 | in-kind |
USFS | Fisheries Biologist (Tech. Team member) | $500 | in-kind |
Sho-Ban Tribes | Fisheries Biologist (Tech. Team member) | $500 | in-kind |
ISCC | Tech. Team member | $500 | in-kind |
Local watermaster | Tech. Team member | $500 | in-kind |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Fundable only if response is adequate
Sep 28, 2001
Comment:
A response is needed for this collection of 6 numbered projects. The fencing projects, screening projects, and some additional actions in the watershed appear warranted and will likely benefit fish. The past actions on fencing the creeks and letting the streams restore themselves without planting or channel modification are justified for those sites. However, the set of proposals goes beyond "flat-tire" fixes. Consequently, the program needs a well-defined watershed assessment and project prioritization effort with a protocol for sampling projects for effectiveness monitoring. Evidence, including data, should be provided that monitoring conducted by other projects is sufficient to evaluate overall trends in numbers of adult and juvenile anadromous species in these subbasins and watersheds. These points are alluded to in the proposal and presentation, but the response should provide more detail.In terms of working with EDT, the sponsors should consider conferring with Bruce Watson of the Yakama Nation fish and wildlife department.
The presentation was broken into a series of sub-presentations based on geography. Most listed the usual list of limiting factors, but did not provide much insight into proposed future actions. The list of opportunities for actions was fairly comprehensive, but did not provide a sense of prioritized actions. Many different agencies are doing many different kinds of monitoring. There seems to be opportunity for improvement and coordination.
The Lemhi has laudatory involvement from local stakeholders, as well as a functioning technical committee in place. There seems to be a disconnect between the "fix the flat-tire" approach and the prioritization effort described in the presentation. Although some problems are obvious, what is the strategy? Should they start at the bottom or top of watershed? Start fixing the portion with best spawning or rearing habitat?
The ISRP does not expect a research level monitoring and evaluation scientific study in this project. Tier I trend monitoring for effectiveness of the project, as described in the introduction to this report, should be sufficient. It may be sufficient to have a regular schedule for checking effectiveness of previous projects, monitoring of water temperatures and cover habitat, etc., e.g., a small systematic sample of projects might be monitored for effectiveness each year so that over a 5 year period, all are surveyed for basic measures.
It does not appear that any of the current monitoring is sufficient to make statistical inferences to these subbasins and watersheds.
The proponents should clarify if or when data from these projects will be available in StreamNet with metadata (methods).
The review group suggests that future terrestrial monitoring efforts be made compatible with one of the national terrestrial survey efforts. Perhaps an intensification of the National Resources Inventory survey sites and data collection protocols would serve the region well. See the Proposals #200002300 and #200020116 and ISRP reviews in the Columbia Plateau.
Comment:
Addresses RPA 149, 150, and 154. See comments for Project Number 28036.Comment:
This collection of numbered proposals are fundable in part for support of the administrative objectives under 199202603. The other objectives and five new proposals are too premature to be reviewed from a scientific point of view at this point in time. Necessary funds and direction should be provided for project 199202603 so that over the next 3 years prioritization of projects and planning, including watershed assessments, are completed.An analysis of the amount of water and bank protection that realistically can be restored should be made. Specialists, such as those presently being consulted, could use this information and attempt to predict what channel characteristics and dynamics might be expected from the expected water and bank restoration. Such an analysis can also show where actions are needed to facilitate development of more favorable fish habitat, and provide a basis for prioritizing projects. Responses to reviewer comments indicated that the proponents are working with channel specialists from the University of Idaho to complete the first steps described above. Successful demonstration that these initial steps have been completed and incorporated into the program should be prerequisite to continued funding.
The ISRP appreciates the commitment to develop a more unified monitoring and evaluation program. These attempts should be coordinated among other projects with aquatic and terrestrial monitoring responsibilities. See the ISRP reviews and proponent's responses to ISRP initial concerns on project proposal #28018. The proponents are referred to the programmatic section of this report on Monitoring, the specific comments on Aquatic Monitoring and Evaluation, and the specific comments on Terrestrial Monitoring and Evaluation.
The Lemhi has laudatory involvement from local stakeholders, as well as a functioning technical committee in place.
In the review of project 28019, the ISRP recommends that projects dealing with animal feeding operations in the Upper Salmon basin be considered for funding as part of Project #199202603 and related proposals submitted by the Custer and Lemhi Soil and Water Conservation Districts. Those projects either have or are developing criteria for effective prioritization of projects for benefit of fish in the subbasin. The ISRP recommends that the Upper Salmon Basin Watershed Project give priority to identifying key feeding operations and to coordinating remediation with their owners and with the ISDA and IOSC and other funding sources.
Comment:
Statement of Potential Biological Benefit to ESULikely increase in survival if improves habitat by addressing water quantity and quality through water renting, fencing, conservation easements, and replanting riparian areas. Difficult to evaluate benefit accurately since proposal doesn't identify where actions will occur.
Comments
Putting in individual proposals for each of the geographic areas in which the model watershed group is a good approach, but there are few details in the proposals as to where and how much land will be affected by these activities, which leads one to question the budget estimates. This subbasin is identified as a priority subbasin in the FCRPS BiOp.
Already ESA Req? No
Biop? Yes
Comment:
Recommend limited funding for habitat projects to implement RPAs 149 and 150. These projects could include riparian easements, riparian exclusion fencing, irrigation diversion consolidation or elimination, and fish passage barrier removal, but exclude active channel restoration. This limited funding would also maintain landowner support for fish recovery, and protect prior habitat investment. Consideration of funding of this project at proposed levels should wait until Subbasin Planning is completed and the need for this project can be properly assessed. BPA RPA RPM:
149, 150
NMFS RPA/USFWS RPM:
149, 150, 154
Comment:
Council recommendation: The ISRP reviewed project 199202603 and the five proposals with new project numbers [28036, 28037, 28038, 28039, 28040] as a package (these are not new projects, they represent ongoing activities that had been restructured with new project numbers -- this is discussed further below). The ISRP found the administrative and implementation support objectives of project 199202603 fundable. The objective of this project is to maintain, enhance, and restore anadromous and resident fish habitat while achieving and maintaining a balance between resource protection and resource use on a holistic watershed management basis. This project serves as the coordinating entity for fish habitat maintenance and enhancement priorities established in the Upper Salmon model watershed plan. The project is coordinated through the Idaho Soil Conservation Commission with the Custer and Lemhi Soil and Water Conservation Districts. The program utilizes a local advisory committee representing private, state, and local land managers and other interests, with a technical advisory team assisting with prioritizing on-the-ground projects.The five "sub-projects" within this package received a "not fundable" recommendation. This collection of proposals contemplated a significant expansion of scope, intensity, and type of activities beyond what had been ongoing in past years. The proposed program would have expanded to over $12 million dollars for Fiscal Year 2002 alone. The ISRP's comments clearly show that it was not comfortable with the significant expansion contemplated for the Upper Salmon River subbasin SWCD program. The ISRP comments reveal that such a substantial expansion could not be scientifically justified without further assessment and planning.
Council staff met with the sponsors, Bonneville staff, and other interests associated with the proposals to evaluate the ISRP comments as well as the Council's general funding considerations. During those discussions the group noted that the ISRP's preliminary report was actually quite supportive of the scope, intensity level, and type of work that had been conducted in the Upper Salmon in past years. The ISRP's preliminary report stated:
The fencing projects, screening projects, and some additional actions in the watershed appear warranted and will likely benefit fish. The past actions on fencing the creeks and letting the streams restore themselves without planting or channel modification are justified for those sites. However, the set of proposals goes beyond "flat-tire" fixes. Consequently, the program needs a well-defined watershed assessment and project prioritization effort with a protocol for sampling projects for effectiveness monitoring.
The sponsors suggested that its Upper Salmon habitat program be scaled back to its previous scope, and to focus on the passive habitat restoration activities that the ISRP determined to be warranted and a benefit to fish. The Council staff agreed that this would be advisable in light of the ISRP recommendations, and staff supports the projects that have been reconfigured in that light. This work continues to be an extremely high priority for the state, managers, and interested parties in the subbasin, and within the province as a whole.
Bonneville comments provided an "A" rating for the administrative project and for each of the five sub-proposals. Bonneville's "A" ranking for the five sub-proposals was conditioned on limiting the scope and nature of the activities to essentially those supported by the ISRP's Preliminary Report recommendations, including riparian easements, riparian exclusion fencing, irrigation diversion consolidation or elimination, and fish passage barrier removal.
In previous funding cycles the Custer and Lemhi Soil and Water Conservation Districts implemented their habitat restoration projects under the following four projects (Administrative #199202603, Habitat #199401700, Passage #199306200, Upper Salmon #199600700). In response to Bonneville staff suggestions, as part of the Mountain Snake project proposal solicitation, the sponsor realigned these projects into one ongoing project (Administrative 199202603) and divided the implementation related work into five separate proposals with new project numbers (Lemhi 28037, Middle Salmon - Panther 28039, Pahsimeroi 28036, East Fork 28038, Upper Salmon 28040). One of the main reasons for this reconfiguration was to better accommodate the proposed substantial expansion in the scope, intensity, and nature of the work. After discussions with the sponsor and scaling back the scope of work in light of ISRP and Bonneville comments, it was agreed that the ongoing work would be better managed with two contracts.
The Council recommends that this work be accomplished through two contracts. The first is ongoing administrative contract #199202603. It should be used to administer funds for the Watershed office. The previously existing habitat project contract #199401700 should be used to administer funds between the Custer and Lemhi Soil and Water Conservation Districts for the on-the-ground project implementation elements that are described in projects # 28036, #28037, #28038, #28039, , and #28040. That contract funding level for 199401700 is the total of the funding recommendations for each of the sub-projects as presented in Table 1. The apportionment of the funds to the various watershed areas can also be determined from the Table 1. funding summary.
Comment:
Fund to implement RPA's 149 and 150. These projects could include riparian management through easements, exclusion fencing or other mechanisms of riparian acquisition or management, irrigation diversion consolidation or elimination, and fish passage barrier removal, but exclude active channel restoration. Since specific projects have not been defined in the proposal, each project must be approved by Bonneville before implementation. Bonneville will require all projects to be reviewed by NMFS for consistency with RPA's 149 and 150. This project will have its own individual contract.Comment:
Included in 199401700. FY 05 increase due to realignment of project work. 200206700, 20026500 and 200206300 linked. Need to align provincial decision to accurate project numbers.Comment:
Basic recommendations on Upper Salmon initially from USBWP in 2002 was $120,000 however there are numerous fencing projects now identified and some diversion modifications. Upper Salmon is a priority area. This includes CSWCD.