FY 2003 Mainstem/Systemwide proposal 200311000
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
35061 Narrative | Narrative |
35061 Sponsor Response to the ISRP | Response |
Sturgeon Overview | Powerpoint Presentation |
Section 1. Administrative
Proposal title | Prophylactic Treatments for White Sturgeon Infected with the White Sturgeon Iridovirus (WSIV) |
Proposal ID | 200311000 |
Organization | U.S. Fish and Wildlife Service (USFWS) |
Proposal contact person or principal investigator | |
Name | Dr. Peter W. Taylor |
Mailing address | 1440 Abernathy Creek Rd Longview, WA 98632 |
Phone / email | 3604256072 / [email protected] |
Manager authorizing this project | Carl Burger |
Review cycle | Mainstem/Systemwide |
Province / Subbasin | Mainstem/Systemwide / |
Short description | This project looks at a number of different prophylactic treatments targeting secondary pathogens found in outbreaks of the White Sturgeon Iridovirus in order to minimize total mortalities. |
Target species | white sturgeon |
Project location
Latitude | Longitude | Description |
---|---|---|
46.22 | -123.1375 | Abernathy Fish Technology Center |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
175 |
184 |
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1998 | Completed a pilot study on the distribution of fish pathogens in hatchery environments |
2001 | Developed a nested PCR for the detection of three fish pathogens, manuscript in press. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
-8650 | White sturgeon mitigation and restoration in the Columbia and Snake Rivers. | This project will supply fertilized eggs and will be a primary beneficiary of data on prophylactic treatments for WSIV and may be able to participate in second-year field trials |
198806400 | Kootenai River White Sturgeon Studies and Conservation Aquaculture | This project will be a primary beneficiary of data on prophylactic treatments and may be able to participate in second-year field trials. |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|---|---|---|---|
1.Installation of test tanks | a. tank purchase (24 tanks) | 0.1 | $7,200 | |
b. installation | 0.1 | $2,000 | ||
2. Installation of sterile room for tissue culture work | a. wiring b. surfacing walls | 0.1 | $2,500 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2003 cost | Subcontractor |
---|---|---|---|---|
1. Evaluate treatments | a. purchase of fry | 0.1 | $3,000 | |
b. feeding and maintenance | 1.0 | $21,992 | ||
c. apply treatments | 1.0 | $10,997 | ||
d. confirm cause of mortalities | 1.0 | $21,992 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Evaluate treatmens | 2004 | 2005 | $57,980 |
Outyear budgets for Monitoring and Evaluation phase
FY 2004 |
---|
$57,980 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2003 cost |
---|---|---|
Personnel | FTE: 1.0, GS-5 Lab technician | $25,525 |
Fringe | $8,940 | |
Supplies | laminar hood for sterile room(8,000.00) | $18,000 |
Travel | $2,000 | |
Indirect | $15,216 | |
$69,681 |
Total estimated budget
Total FY 2003 cost | $69,681 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2003 budget request | $69,681 |
FY 2003 forecast from 2002 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|---|---|---|
USFWS | 0.3 FTE, GS-12, microbiologist | $21,166 | in-kind |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Do not fund - no response required
Aug 2, 2002
Comment:
Not Fundable. The proposal was inadequate. This is a very short proposal to do routine screening of prophylactics for their efficacy in treating secondary bacterial and fungal infections of white sturgeon undergoing effects of a viral infection. Such checking of prophylactics doesn't seem to be cutting edge research. The prophylactics are commonly used on other fish for similar infections. No literature documentation is provided for this common practice.Comment:
see review for Proposal 35059Comment:
Do Not Fund; agree with CBFWA. The proposal is inadequate. This is a very short proposal to do routine screening of prophylactics for their efficacy in treating secondary bacterial and fungal infections of white sturgeon undergoing effects of a viral infection. Such checking of prophylactics doesn't seem to be cutting edge research. The prophylactics are commonly used on other fish for similar infections. No literature documentation is provided for this common practice.Comment:
Statement of Potential Biological BenefitComments
Not Reviewed
Already ESA Required?
Biop?
No
Comment:
Category:3. Other projects not recommended by staff
Comments: