FY 1999 proposal 9050
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
9050 Narrative | Narrative |
Section 1. Administrative
Proposal title | Remove 23 Migrational Barriers and Restore Riparian Vegetation on Chumstick |
Proposal ID | 9050 |
Organization | U.S. Fish and Wildlife Service (USFWS) |
Proposal contact person or principal investigator | |
Name | Kate Terrell |
Mailing address | P.O. Box 1157 Moses Lake, WA 98837 |
Phone / email | 5097656125 / [email protected] |
Manager authorizing this project | |
Review cycle | FY 1999 |
Province / Subbasin | Upper Mid-Columbia / Wenatchee |
Short description | Enhance and restore fish passage in the Chumstick Drainage. Species that will be affected include chinook, steelhead, bull trout, westslope cutthroat, and re-introduced coho. |
Target species |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|
Section 3. Relationships to other projects
Project ID | Title | Description |
---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 1999 cost |
---|---|---|
Subcontractor | $200,000 | |
$200,000 |
Total estimated budget
Total FY 1999 cost | $200,000 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 1999 budget request | $200,000 |
FY 1999 forecast from 1998 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Other budget explanation
Schedule Constraints: It will be necessary that all in-stream work be completed during the work window established by Washington Department of Fish and Wildlife.
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Return to Sponsor for Revision
May 13, 1998
Comment:
Technical Issue: Need to explicitly state the existing resource condition, whether the culverts are a critical limiting factor, and how that determination was made.Technical Issue: Need to describe the measurable benefits of culvert removal to fish and wildlife.
Comment:
Budget constraints. Proposal was found to be technically sound and appropriate but was deferred because other work was judged more urgent and funds were not adequate for all needed work.Comment:
The sequence of objective and tasks were well described. The proposed monitoring program was adequate. This was a good proposal. The ISRP strongly recommends funding this project.