FY 1999 proposal 199305600
Section 1. Administrative
Proposal title | Assessment of Captive Broodstock Technology |
Proposal ID | 199305600 |
Organization | National Marine Fisheries Service, NOAA, DOC (NMFS) |
Proposal contact person or principal investigator |
Name | Penny Swanson |
Mailing address | 2725 Montlake Blvd. East Seattle, WA 98112-2097 |
Phone / email | 2068603282 / [email protected] |
Manager authorizing this project | |
Review cycle | FY 1999 |
Province / Subbasin | Systemwide / Systemwide |
Short description | Improve effectiveness and assess risks of captive broodstock programs as a tool for recovery of depleted salmon stocks |
Target species | Snake River Spring and Summer Chinook Salmon, Redfish Lake Sockeye Salmon, and any other listed stocks. |
Project location
Latitude | Longitude | Description |
Reasonable and Prudent Alternatives (RPAs)
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
Section 2. Past accomplishments
Section 3. Relationships to other projects
Project ID | Title | Description |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 1999 cost |
Personnel |
|
$260,600 |
Fringe |
|
$102,416 |
Supplies |
|
$78,322 |
Capital |
|
$3,200 |
Travel |
|
$13,600 |
Indirect |
|
$140,224 |
Subcontractor |
|
$575,500 |
Other |
|
$26,138 |
| $1,200,000 |
Total estimated budget
Total FY 1999 cost | $1,200,000 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 1999 budget request | $1,200,000 |
FY 1999 forecast from 1998 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
Other budget explanation
Schedule Constraints: None anticipated.
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Recommendation:
Date:
May 13, 1998
Comment:
Criteria 1: Technical Criteria - Yes
Criteria 2: Objectives Criteria - Yes
Criteria 3: Milestones Criteria - Yes
Criteria 4: Resources Criteria - Incomplete: Since the subcontractors are the largest budget item, need subcontractors resumes and their involvement.
Recommendation:
Fund
Date:
May 13, 1998
Comment:
Recommendation:
Adequate
Date:
Jun 18, 1998
Comment:
This is a good proposal with good objectives, and it ranked in the top 10 of the set. It is well related to the Fish and Wildlife Program and NMFS Recovery Plan. The abstract is good but the proposal is too long. The background and methods are also too long and detailed but are very informative.
REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$1,468,100 |
$1,468,100 |
$1,468,100 |
Sponsor comments: See comment at Council's website