FY 1999 proposal 199401805

Additional documents

TitleType
199401805 Narrative Narrative

Section 1. Administrative

Proposal titleEnhance Habitat For Spring Chinook, Summer Steelhead, and Bulltrout
Proposal ID199401805
OrganizationAsotin County Conservation District (ACCD)
Proposal contact person or principal investigator
NameBradley J. Johnson
Mailing address725 6th St, Suite 102 Clarkston, WA 99403
Phone / email5097588012 / [email protected]
Manager authorizing this project
Review cycleFY 1999
Province / SubbasinLower Snake / Asotin
Short descriptionEnhance fish habitat, reduce water temperatures, erosion and sedimentation, improve and re-establish riparian vegetation, and promote cooperation and agreement between landowners and resource agencies within the Asotin Creek watershed..
Target speciesSpring chinook salmon, summer steelhead, and bulltrout
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription
9202602 Implement Eastern Washington Model Watershed Plans Technical Lead to Implement Plan. Project helps implement Plan and Habitat restoration in T&E chinook and steelhead streams. Builds community wide support in watershed restoration.

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 1999 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 1999 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 1999 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 1999 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 1999 cost
Operating $15,000
Subcontractor Earth Conservation Corps, Salmon Corp; W.A. State Department of Fish & Wildlife; U.S. Forest Service; Asotin County Commissioners; WSU Analytical Lab; Natural Resource Conservation Service; WSU-Center for Environmental Education $96,000
Other $82,000
Other $82,000
Other $82,000
Other $82,000
Other $82,000
Other $82,000
Other $82,000
$685,000
Total estimated budget
Total FY 1999 cost$685,000
Amount anticipated from previously committed BPA funds$0
Total FY 1999 budget request$685,000
FY 1999 forecast from 1998$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
Other budget explanation

Schedule Constraints: Improving and maintaining critical habitat requires cooperation and long-term commitments between landowners, state and federal agencies for watershed management. Cooperators need to know that long-term cost-share assistance will be available.


Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Return to Sponsor for Revision
Date:
May 13, 1998

Comment:

Technical Issue: Describe if the objectives, tasks, and funding have changed from FY98 – the schedule describes project completion by the end of FY98.

Technical Issue: Resubmit the proposal based on approved funding in FY98, if funds for FY99 are justifiably needed.


Recommendation:
Fund
Date:
May 13, 1998

Comment:

Absorbs part of 9202602
Recommendation:
Adequate after revision
Date:
Jun 18, 1998

Comment:

This proposal does not adequately describe the technical justification for the proposed actions. Benefits to fish and wildlife are not well explained.
REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$280,214 $280,214 $280,214

Sponsor comments: See comment at Council's website