FY 1999 proposal 199700100
Section 1. Administrative
Proposal title | Captive Rearing Initiative for Salmon River Chinook Salmon |
Proposal ID | 199700100 |
Organization | Idaho Department of Fish and Game (IDFG) |
Proposal contact person or principal investigator |
Name | Paul A. Kline |
Mailing address | 1800 Trout Rd. Eagle, ID 83616 |
Phone / email | 2089394114 / [email protected] |
Manager authorizing this project | |
Review cycle | FY 1999 |
Province / Subbasin | Lower Snake / Salmon |
Short description | Establish captive rearing protocols for Salmon River Chinook salmon. Rear juveniles to maturation, release mature adult chinook back into streams of origin. Monitor spawning success of released adults. |
Target species | |
Project location
Latitude | Longitude | Description |
Reasonable and Prudent Alternatives (RPAs)
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
Section 2. Past accomplishments
Section 3. Relationships to other projects
Project ID | Title | Description |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 1999 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 1999 cost |
Personnel |
|
$26,935 |
Fringe |
|
$9,319 |
Supplies |
|
$10,300 |
Operating |
|
$32,010 |
Capital |
|
$41,200 |
Tag |
|
$1,450 |
Travel |
|
$5,550 |
Indirect |
|
$18,225 |
Subcontractor |
|
$0 |
| $144,989 |
Total estimated budget
Total FY 1999 cost | $144,989 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 1999 budget request | $144,989 |
FY 1999 forecast from 1998 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
Other budget explanation
Schedule Constraints: No known constraints - Start/stop dates identified above reflect FY99 only.
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Recommendation:
Date:
May 13, 1998
Comment:
Criteria 1: Technical Criteria - Yes
Criteria 2: Objectives Criteria - Yes
Criteria 3: Milestones Criteria - Yes
Criteria 4: Resources Criteria - Yes: Clarify budget - Report 28k
Recommendation:
Fund
Date:
May 13, 1998
Comment:
Recommendation:
Adequate
Date:
Jun 18, 1998
Comment:
These proposals [199700100 and 199801002] are for a captive rearing program to preserve endangered stocks of Snake River chinook salmon. The proposals do not reference relevant NMFS studies on captive rearing. Captive rearing is a new approach and should be implemented cautiously. The relationship of 9700100 to 9801002 needs to be better described. 9801002 includes what appears to be a good monitoring and evaluation project. The research and monitoring should come before full-scale supplementation actions. This project should be combined with those for which it is intended to provide monitoring and evaluation, so that overall soundness of the project, including its evaluation aspects, can be judged.
REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$509,000 |
$509,000 |
$509,000 |
Sponsor comments: See comment at Council's website