FY 2000 proposal 20535

Additional documents

TitleType
20535 Narrative Narrative

Section 1. Administrative

Proposal titleMulti-Year Salmon Anadromous Fish Plan
Proposal ID20535
OrganizationColumbia Basin Fish & Wildlife Authority (CBFWA)
Proposal contact person or principal investigator
NameTom Giese
Mailing address2501 SW First Ave., Suite 200 Portland, OR 97201
Phone / email5032290191 / [email protected]
Manager authorizing this project
Review cycleFY 2000
Province / SubbasinMountain Snake / Salmon
Short description
Target species
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription
9107100 Determine sockeye carrying capacity for nursery lakes in Salmon basin.
9703800 Preserve chinook gametes by cryo-preservation.
9703000 Compare adult chinook returns via passive underwater video.
8909800 Evaluate usefulness of supplementation as recovery/restoration method.
8909801 Evaluate usefulness of supplementation as recovery/restoration method.
8909802 Evaluate usefulness of supplementation as recovery/restoration method.
8909803 Evaluate usefulness of supplementation as recovery/restoration method.
9005500 Evaluate usefulness of supplementation as recovery/restoration method.
9204000 Captive rearing to aid in recovery of Stanley Basin sockeye.
9064 Describe factors influencing distribution/persistence of wild chinook
9107200 Captive rearing to aid in recovery of Stanley Basin sockeye.
9405000 Habitat enhancement/restoration at multiple sites, conduct O&M and M&E
9801002 Captive rearing monitoring.
9107300 Continue monitoring natural production in Salmon & Clearwater subbasins.
20535 MYP Salmon Anadromous Fish Plan
9401500 Construction/maintenance of screens, pumps, fish ladders, surveys.
9606700 Implement side stream incubation and captive broodstock rearing.
9009 Restore healthy riparian corridor along 12 mi. of Salmon River.
9202603 Support Idaho Model Watershed administration and coordination.
9401700 Implement habitat restoration in Lemhi, Pahsimeroi, East Fork drainages.
9202408 Implement tribal law enforcement activities to protect fishery.
9600700 Eliminate 3 diversions and install pump on Salmon River.
9306200 Habitat enhancement to increase flow, reduce barriers, restore riparian veg
9401700 Habitat enhancement to increase flow, reduce barriers, restore riparian veg
9604300 Increase survival of weak summer chinook stocks on Johnson Creek.
9705700 Implement side stream incubation and captive broodstock rearing.
9700100 Implement side stream incubation and captive broodstock rearing.

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2000 cost
Personnel $0
Fringe $0
Supplies $0
$0
Total estimated budget
Total FY 2000 cost$0
Amount anticipated from previously committed BPA funds$0
Total FY 2000 budget request$0
FY 2000 forecast from 1999$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
NA - Umbrella Proposal
Date:
Jun 15, 1999

Comment:

Recommendation: NA - Umbrella Proposal

Comments: Five ostensibly "outcome-based" objectives are listed that the co-managers have adopted to address the problems identified in the proposal. The fifth of these is: "supplement where needed with genetically-appropriate salmon and steelhead in the subbasin using stock specific escapement criteria capable of maintaining stock productivity, survival and genetic diversity." This objective is in fact not outcome-based, but rather states foremost the expected performance of an activity (supplementation). The emphasis appears to be on keeping technical programs going rather than on achieving results. The underlying outcome-based objective, if a valid one exists (it may be hinted at in the last part of the quoted sentence), should be made clear in a re-casting of this fifth item.


Recommendation:
Do Not Fund
Date:
Aug 20, 1999

Comment:


Recommendation:
Date:
Aug 20, 1999

Comment:

Criteria all: Met? N/A -