Proposal title | Protect and Enhance Anadromous Fish Habitat in The John Day Subbasin |
Proposal ID | 198402100 |
Organization | Oregon Department of Fish and Wildlife (ODFW) |
Proposal contact person or principal investigator |
Name | Jeff Neal |
Mailing address | PO Box 515 John Day, OR 97845 |
Phone / email | 5415750561 / [email protected] |
Manager authorizing this project | Bruce Eddy |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Columbia Plateau / John Day |
Short description | Implement long-term riparian, fish habitat and tributary passage improvement on private lands within the John Day Subbasin. |
Target species | |
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
Obj. 1. Develop plans for enhancing fish habitat and riparian areas. |
Task 1.1. Develop "reference reach" data to determinie functionality and stability of project streams. |
3-5 |
$7,500 |
|
|
Task 1.2. Work cooperatively with private landowners to develop long-term riparian leases, cooperative agreements or easements. |
On-going |
$7,500 |
|
|
Task 1.3. Conduct Rosgen (1996) level III assessment of instream project streams. |
On-going |
$4,000 |
|
|
Task 1.4. Conduct project design surveys. |
On-going |
$3,801 |
|
|
Task 1.5. Develop instream project designs. |
On-going |
$5,000 |
Yes |
|
Task 1.6. Prepare contract documents and specifications. |
On-going |
$20,034 |
Yes |
|
Task 1.7. Complete NEPA |
On-going |
$5,000 |
|
Obj 2. Develop plans for maintaining fish habitat improvement projects. |
Task 2.1. Prepare contract documents and specifications. |
On-going |
$1,500 |
|
|
Task 2.2 conduct on-site preparation activities. |
On-going |
$2,500 |
|
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
Obj. 1. Improve stream channel function, instream habitat diversity and streambank stability by constructing bioengineering treatments, instream structures and placing large wood. |
Task 1.1. Remove, transport and level dredge tailings along Granite Creek. |
1 |
$55,845 |
Yes |
|
Task 1.2. Spread soil uncovered in task 1.1 over all disturbed sites. |
1 |
$23,119 |
Yes |
|
Task 1.3. Place all excavated trees and boulders instream for fish habitat. |
1 |
$25,000 |
Yes |
Objective 2. Improve the quantity and quality of riparian communities along the John Day River and tributaries |
Task 2.1. Construct approximately 6 miles of riparian corridor fencing to exclude livestock. |
1 |
$85,000 |
Yes |
|
2.2. Develop off-site livestock water developments to better utilize range resources and remove pressure from riparian zones. |
1 |
$20,000 |
Yes |
|
Task 2.3. Revegetate 3 miles of riparian areas by seeding and planting. |
1 |
$10,000 |
|
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
Obj. 1. Provide maiximum project benefits by providing maintenance on existing projects. |
Task 1.1. Inspect 100.2 miles of fence and conduct maintenance on 23 miles. |
On-going |
$41,401 |
|
|
Task 1.2. Inspect 120 watergaps and conduct maintenance on 20. |
On-going |
$26,401 |
|
|
Task 1.3. Inspect 22 spring developments and conduct maintenance on 6. |
On-going |
$7,500 |
|
|
Task 1.4. Coordinate O & M activities with private landowners. |
On-going |
$7,500 |
|
|
Task 1.5. Inspect completed instream work and conduct maintenance where necessary. |
On-going |
$2,500 |
|
|
Task 1.6. Repair and maintain project vehicles, tools and equipment. |
On-going |
$6,655 |
|
|
Task 1.4 Inspect 246.2 acres for noxious weeds and control on 45 acres |
On-going |
$5,000 |
|
Obj. 2. Provide administrative oversight and secretarial support for project activities. |
Task 2.1. Prepare and review all contract documents, competitive bid packages, riparian leases and reports. |
On-going |
$4,000 |
|
|
Task 2.2. Prepare annual work statements and budgets for submittal to BPA. |
On-going |
$7,500 |
|
|
Task 2.3 Liaison with BPA, federal and state agencies and tribes on issues that effect successful implementation of on-the-ground projects. |
On-going |
$2,000 |
|
|
Task 2.4 Supervision of project personnel. |
On-going |
$4,000 |
|
|
Task 2.5. Provide secretarial support for project activities |
On-going |
$2,000 |
|
|
Task 2.6 Provide offices and support services for project personnel |
On-going |
$3,000 |
|
|
Task 2.7. Develop project procedures and protocols for development, maintenance and construction of projects. |
On-going |
$2,500 |
|
Obj. 3. Insure maximum communication, education and coordination of habitat enhancement activities by actively pursuing opportunities to work with, educate and learn from individuals and entities. |
Task 3.1. Work cooperatively with the SWCD to identify and prioritize projects. |
On-going |
$5,000 |
|
|
Task 3.2. Coordinate field activities with other agencies. |
On-going |
$5,000 |
|
|
Task 3.3. Answer correspondence, respond to information needs and make presentations to other agencies, private organizations, school/youth groups and the news media. |
|
$2,500 |
|
|
Task 3.4. Work cooperatively with private landowners to promote projects and management activities beneficial to the protection and restoration of fish habitat. |
On-going |
$7,317 |
|
Item | Note | FY 2001 cost |
Personnel |
FTE: .29 NRS2, .13 Tech II, ..08 SFWB |
$22,083 |
Fringe |
|
$8,811 |
Supplies |
|
$2,200 |
Travel |
Vehilce lease and mileage |
$1,290 |
Indirect |
|
$9,011 |
NEPA |
|
$5,000 |
Subcontractor |
Grant SWCD |
$7,000 |
Other |
Training - Rosgen Level 4 |
$1,440 |
Personnel |
FTE: .25 NRS 2, .25 Tech 2, .08 Tech 1 |
$21,722 |
Fringe |
|
$8,667 |
Supplies |
Fence materials, seeds, plants, etc. |
$44,250 |
Travel |
Vehcle lease, mileage, perdiem |
$3,510 |
Indirect |
|
$20,788 |
Subcontractor |
Heavy equipment contractors, fence contractors, etc. |
$120,027 |
Personnel |
FTE: .38 NRS 2, .54 Tech II, .67 Tech I, .13 SFWB, .08 Clerical Specialist |
$59,074 |
Fringe |
|
$23,570 |
Supplies |
|
$15,131 |
Travel |
Vehicle lease, mileage, perdiem |
$11,310 |
Indirect |
|
$29,219 |
Subcontractor |
Equipment and labor contractors |
$2,710 |
Other |
Training |
$760 |
Personnel |
FTE: .08 NRS 2, .08 Tech II, .07 SFWB |
$10,330 |
Fringe |
|
$4,122 |
Supplies |
|
$1,500 |
Travel |
|
$430 |
Indirect |
|
$4,541 |
Other |
Taining - Rosgen level 4 |
$1,440 |
| $439,936 |
This information was not provided on the original proposals, but was generated during the review process.