Section 1. Administrative
Proposal title | Pacific Lamprey Reasearch and Restoration Project |
Proposal ID | 199402600 |
Organization | Confederated Tribes of the Umatilla Indian Reservation (CTUIR) |
Proposal contact person or principal investigator |
Name | David Close |
Mailing address | Pendleton, OR 97801 |
Phone / email | 5412787615 / [email protected] |
Manager authorizing this project | Gary James |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Columbia Plateau / Umatilla |
Short description | Implement and monitor Pacific lamprey restoration plan developed for the Umatilla River. Assess ability of Pacific lampreys to detect pheromone emitted by larvae. |
Target species | |
Project location
Latitude | Longitude | Description |
Reasonable and Prudent Alternatives (RPAs)
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
Section 2. Past accomplishments
Year | Accomplishment |
1995 |
Completion of Pacific lamprey Status Report. |
1996 |
Tested clinical indicators of stress in Pacific lampreys. |
1997 |
Completed assessment of radio-tagged Pacific lampreys using clinical indicators and swimming performance. |
1998 |
Completed assessment of ability of adult Pacific lampreys to detect pheromones and larval production of pheromones. |
1999 |
Completed genetic analysis using allozyme and mtdna. |
1999 |
Completed radio-tracking study to assess migrational behavior. |
1999 |
Completed distribution and point sample densities in the John Day, Umatilla, Walla Walla, Tucannon, and Grande Ronde Rivers. |
1999 |
Completed oral histories with tribal members. |
1999 |
Completed Columbia Basin Pacific lamprey projects and needs assessment through Technical Work Group (TWG). |
1999 |
Completed restoration plan for the Umatilla River, Oregon. |
Section 3. Relationships to other projects
Project ID | Title | Description |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
1. Estimate lamprey abundance before and after outplanting adults in the Umatilla River. |
a) Estimate numbers of adult lampreys entering the Umatilla River.
|
1998-2005 |
$33,994 |
|
|
b) Estimate densities of lamprey larvae in index plots in the Umatilla River.
|
1998-2005 |
$39,660 |
|
|
c) Estimate numbers of recently metamorphosed larvae out migrating
|
1999-2005 |
$33,994 |
|
|
d) Sample river water in the Umatilla River for migratory pheromone. |
1999-2005 |
$5,665 |
|
2. Increase larval abundance in the Umatilla River. |
a) Release sexually mature lampreys in the Umatilla River. |
2000-2005 |
$22,663 |
|
|
b) Monitor larvae in cages. |
2000-2001 |
$20,396 |
|
|
c) Coordinate with Umatilla River operations personnel to increase flows through dewatered sections. |
indefinite |
$2,266 |
|
3. Determine reproductive success of adult outplants. |
a) Conduct redd surveys |
2000-2005 |
$19,912 |
|
|
b) Document spawning activity |
2000-2005 |
$19,912 |
|
|
c) Estimate percent egg viability |
2000-2005 |
$13,274 |
|
|
d) Determine fecundities |
2000-2005 |
$13,274 |
|
4. Determine adult lamprey abundance in the Columbia River at the John Day Dam. |
a) Install traps |
2001 |
$22,663 |
|
|
b) Check traps |
2001-2005 |
$54,391 |
|
|
c) Analysis of data |
2001-2005 |
$13,597 |
|
5. Assess artificial propagation using Pacific lampreys. |
a) Develop artificial production manual for Pacific lampreys. |
2001-2002 |
$22,663 |
|
6. Measure the temporal variations in the responses of upstream migrating Pacific lampreys using electro-olfactogram (EOG) techniques. |
a) Collect upstream migrating Pacific lampreys from the lower Columbia River.
|
2000-2002 |
$11,493 |
|
|
b) Receive training from Dr. Peter Sorensen regarding EOG system and operation. |
2000-2001 |
$11,493 |
|
|
c) Collect larval lampreys from the John Day River |
2000-2001 |
$11,493 |
|
|
d) Measure the responses of bile salts of lampreys during the process of sexual maturation. |
2000-2002 |
$80,464 |
|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
Outyear budgets for Monitoring and Evaluation phase
FY 2004 | FY 2005 | FY 2002 | FY 2003 |
---|
$539,847 | $572,237 | $480,464 | $509,290 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2001 cost |
Personnel |
FTE: 4.4 |
$150,007 |
Fringe |
|
$44,232 |
Supplies |
|
$13,833 |
Travel |
|
$29,489 |
Indirect |
|
$80,771 |
Subcontractor |
|
$20,000 |
Subcontractor |
|
$114,935 |
| $453,267 |
Total estimated budget
Total FY 2001 cost | $453,267 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2001 budget request | $453,267 |
FY 2001 forecast from 2000 | $408,000 |
% change from forecast | 11.1% |
Reason for change in estimated budget
The increase is in part due to expanded need for travel/vehicles to accomplish increased tasks. The lamprey project currently has one GSA vehicle. This is inadequate to address the necessary project tasks listed above. We are in the initial stages of implementing the lamprey restoration plan for the Umatilla River which has added more monitoring and evaluation. We are working to accomplish many new objectives and tasks to evaluate the outplanting adults in the Umatilla River.
Reason for change in scope
Finalization of the Restoration plan for Pacific lampreys in the Umatilla River in 1999 identified additional necessary monitoring and evaluation tasks that were not identified when initial FY 2001 Budget projection was made in 1998. Additional tasks now proposed include; 2abc, 3abcd,
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Recommendation:
Ongoing Funding: yes; New Funding: yes
Date:
Jul 14, 2000
Comment:
The increase is in part due to expanded need for travel/vehicles to accomplish increased tasks. The lamprey project currently has one GSA vehicle. This is inadequate to address the necessary project tasks listed above. We are in the initial stages of implementing the lamprey restoration plan for the Umatilla River which has added more monitoring and evaluation. We are working to accomplish many new objectives and tasks to evaluate the outplanting adults in the Umatilla River.Finalization of the restoration plan for Pacific lampreys in the Umatilla River in 1999 identified additional necessary monitoring and evaluation tasks that were not identified when the initial FY 2001 Budget projection was made in 1998. Additional tasks now proposed include; 2abc ($45,325), 3abcd ($66,372). The MainSys SRT has flagged these new tasks to insure that they have been technically reviewed. A lamprey master plan was recently completed and technical review may have been completed in that forum.
Recommendation:
Fund
Date:
Sep 13, 2000
Comment:
Tasks should be categorized as a research project, not M&E.
REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$501,090 |
$501,090 |
$501,090 |
Sponsor comments: See comment at Council's website