FY 2001 Ongoing proposal 199402600

Additional documents

TitleType

Section 1. Administrative

Proposal titlePacific Lamprey Reasearch and Restoration Project
Proposal ID199402600
OrganizationConfederated Tribes of the Umatilla Indian Reservation (CTUIR)
Proposal contact person or principal investigator
NameDavid Close
Mailing address Pendleton, OR 97801
Phone / email5412787615 / [email protected]
Manager authorizing this projectGary James
Review cycleFY 2001 Ongoing
Province / SubbasinColumbia Plateau / Umatilla
Short descriptionImplement and monitor Pacific lamprey restoration plan developed for the Umatilla River. Assess ability of Pacific lampreys to detect pheromone emitted by larvae.
Target species
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
1995 Completion of Pacific lamprey Status Report.
1996 Tested clinical indicators of stress in Pacific lampreys.
1997 Completed assessment of radio-tagged Pacific lampreys using clinical indicators and swimming performance.
1998 Completed assessment of ability of adult Pacific lampreys to detect pheromones and larval production of pheromones.
1999 Completed genetic analysis using allozyme and mtdna.
1999 Completed radio-tracking study to assess migrational behavior.
1999 Completed distribution and point sample densities in the John Day, Umatilla, Walla Walla, Tucannon, and Grande Ronde Rivers.
1999 Completed oral histories with tribal members.
1999 Completed Columbia Basin Pacific lamprey projects and needs assessment through Technical Work Group (TWG).
1999 Completed restoration plan for the Umatilla River, Oregon.

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
1. Estimate lamprey abundance before and after outplanting adults in the Umatilla River. a) Estimate numbers of adult lampreys entering the Umatilla River. 1998-2005 $33,994
b) Estimate densities of lamprey larvae in index plots in the Umatilla River. 1998-2005 $39,660
c) Estimate numbers of recently metamorphosed larvae out migrating 1999-2005 $33,994
d) Sample river water in the Umatilla River for migratory pheromone. 1999-2005 $5,665
2. Increase larval abundance in the Umatilla River. a) Release sexually mature lampreys in the Umatilla River. 2000-2005 $22,663
b) Monitor larvae in cages. 2000-2001 $20,396
c) Coordinate with Umatilla River operations personnel to increase flows through dewatered sections. indefinite $2,266
3. Determine reproductive success of adult outplants. a) Conduct redd surveys 2000-2005 $19,912
b) Document spawning activity 2000-2005 $19,912
c) Estimate percent egg viability 2000-2005 $13,274
d) Determine fecundities 2000-2005 $13,274
4. Determine adult lamprey abundance in the Columbia River at the John Day Dam. a) Install traps 2001 $22,663
b) Check traps 2001-2005 $54,391
c) Analysis of data 2001-2005 $13,597
5. Assess artificial propagation using Pacific lampreys. a) Develop artificial production manual for Pacific lampreys. 2001-2002 $22,663
6. Measure the temporal variations in the responses of upstream migrating Pacific lampreys using electro-olfactogram (EOG) techniques. a) Collect upstream migrating Pacific lampreys from the lower Columbia River. 2000-2002 $11,493
b) Receive training from Dr. Peter Sorensen regarding EOG system and operation. 2000-2001 $11,493
c) Collect larval lampreys from the John Day River 2000-2001 $11,493
d) Measure the responses of bile salts of lampreys during the process of sexual maturation. 2000-2002 $80,464
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase
FY 2004FY 2005FY 2002FY 2003
$539,847$572,237$480,464$509,290

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2001 cost
Personnel FTE: 4.4 $150,007
Fringe $44,232
Supplies $13,833
Travel $29,489
Indirect $80,771
Subcontractor $20,000
Subcontractor $114,935
$453,267
Total estimated budget
Total FY 2001 cost$453,267
Amount anticipated from previously committed BPA funds$0
Total FY 2001 budget request$453,267
FY 2001 forecast from 2000$408,000
% change from forecast11.1%
Reason for change in estimated budget

The increase is in part due to expanded need for travel/vehicles to accomplish increased tasks. The lamprey project currently has one GSA vehicle. This is inadequate to address the necessary project tasks listed above. We are in the initial stages of implementing the lamprey restoration plan for the Umatilla River which has added more monitoring and evaluation. We are working to accomplish many new objectives and tasks to evaluate the outplanting adults in the Umatilla River.

Reason for change in scope

Finalization of the Restoration plan for Pacific lampreys in the Umatilla River in 1999 identified additional necessary monitoring and evaluation tasks that were not identified when initial FY 2001 Budget projection was made in 1998. Additional tasks now proposed include; 2abc, 3abcd,

Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Ongoing Funding: yes; New Funding: yes
Date:
Jul 14, 2000

Comment:

The increase is in part due to expanded need for travel/vehicles to accomplish increased tasks. The lamprey project currently has one GSA vehicle. This is inadequate to address the necessary project tasks listed above. We are in the initial stages of implementing the lamprey restoration plan for the Umatilla River which has added more monitoring and evaluation. We are working to accomplish many new objectives and tasks to evaluate the outplanting adults in the Umatilla River.

Finalization of the restoration plan for Pacific lampreys in the Umatilla River in 1999 identified additional necessary monitoring and evaluation tasks that were not identified when the initial FY 2001 Budget projection was made in 1998. Additional tasks now proposed include; 2abc ($45,325), 3abcd ($66,372). The MainSys SRT has flagged these new tasks to insure that they have been technically reviewed. A lamprey master plan was recently completed and technical review may have been completed in that forum.


Recommendation:
Fund
Date:
Sep 13, 2000

Comment:

Tasks should be categorized as a research project, not M&E.
REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$501,090 $501,090 $501,090

Sponsor comments: See comment at Council's website