FY 2001 Ongoing proposal 199500700

Additional documents

TitleType

Section 1. Administrative

Proposal titleHood River Production Program - PGE: O&M
Proposal ID199500700
OrganizationPortland General Electric - Enron (PGE)
Proposal contact person or principal investigator
NameBill May
Mailing address121 SW Salmon St Portland, OR 97204
Phone / email5034647546 / [email protected]
Manager authorizing this projectBill May
Review cycleFY 2001 Ongoing
Province / SubbasinColumbia Plateau / Deschutes
Short descriptionThis project reimburses PGE for the use of hatchery facilities at the Pelton - Round Butte hatchery and extended rearing facilities and for the cost of rearing approximatley 225,000 spring Chinook for BPA to be released into the Deschutes and Hood Rivers.
Target species
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
1995 Met production objectives for both the Deschutes and Hood River systems
1999 Met production objectives for both the Deschutes and Hood River systems

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Ladder O&M by PGE a continious $15,700
Hatchery O&M by PGE a continious $3,700
Housing & vehicle PGE a continious $13,340
Early Fish Tank Enclosure a One time action $7,500 Yes
Hatchery Resident Heating and Cooling a One time Action $6,250 Yes
Fish Trap Area Enclosure a One time Action $1,500
Administration of ODFW ops by PGE (3%) a continious $3,527
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase
FY 2003FY 2005FY 2004FY 2002
$50,000$60,000$55,000$45,000

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2001 cost
Capital N/A $0
NEPA N/A $0
Other PGE costs $51,517
Personnel FTE: N/A $0
$51,517
Total estimated budget
Total FY 2001 cost$51,517
Amount anticipated from previously committed BPA funds$0
Total FY 2001 budget request$51,517
FY 2001 forecast from 2000$85,000
% change from forecast-39.4%
Reason for change in estimated budget

The number of facility upgrades were less than expected.

Reason for change in scope

See above.

Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Ongoing Funding: yes; New Funding: no
Date:
Jul 14, 2000

Comment:

Budget is less than FY 2001 forecast. The number of facility upgrades were less than expected. There is no change in scope of work.
Recommendation:
Absorb 198902900
Date:
Sep 8, 2000

Comment:

To efficiently coordinate, implement and manage the BPA funded activities associated with the Pelton Ladder - Round Butte Hatchery Complex project number 199500700 (PGE) and 198902900 (ODFW) should be consolidated into one contract under project number 199500700.
Recommendation:
Fund
Date:
Sep 13, 2000

Comment:


Recommendation:
Do Not Fund
Date:
Sep 20, 2003

Comment:

Total for the budget is 150K, which appears to cover both projects. Drop this project, based on PGE comments.
Recommendation:
Date:
Sep 20, 2003

Comment: