FY 2001 Ongoing proposal 199501300

Additional documents

TitleType

Section 1. Administrative

Proposal titleNez Perce Tribe Resident Fish Substitution Program
Proposal ID199501300
OrganizationNez Perce Tribe (NPT)
Proposal contact person or principal investigator
NameTod Sween
Mailing address Lapwai, ID 83541
Phone / email2088437144 / [email protected]
Manager authorizing this projectSilas Whitman
Review cycleFY 2001 Ongoing
Province / SubbasinMountain Snake / Clearwater
Short descriptionIncrease fish harvest opportunities to partially mitigate for anadromous fisheries losses resulting from the "permanent" migration blockage posed by Dworshak Dam on the North Fork Clearwater River.
Target species
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment
1997 Completed restoration of the Talmaks Reservoir fishery, increasing carrying capacity, harvest, and health of this fishery.
1998 Initiated restoration of the Mud Springs Reservoir fishery.
1999 Completed restoration of the Mud Springs Reservoir fishery.
1999 Completed construction of the new Tunnel Pond.

Section 3. Relationships to other projects

Project IDTitleDescription

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
1. Manage and monitor the pond habitat and fish at existing facilities to support the annual harvest goal of 4750 kg of resident salmonids. a. Monitor temperature, oxygen, depth, and other pertinent chemical, biological, and habitat parameters in order to manage existing fisheries. 5 $51,930
b. Monitor and evaluate effects of watershed use on water quality and habitat quantity. Assess fisheries response to land use practices (grazing, logging,and agricultural) in the watershed and gauge implemented best management practices (BMPs). 5 $12,984
c. Conduct periodic site maintenance to maintain structural integrity of the dams and pond sites, assure access, and maintain habitat quality to maximize potential carrying capacity and fish harvest. 5 $38,950
d. Monitor fish growth and condition. reflecting health of the fish. 5 $25,965
2. Manage and monitor fisheries at existing resident fish pond facilities to provide 4750 kg of resident salmonids annually. e. Monitor harvest 5 $103,860
f. Evaluate and refine individual fishery management and stocking plans based on fish health, growth, condition (Task d), and harvest information (Task e) to maximize fish growth, condition, and harvest. 5 $25,965
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase
FY 2003FY 2005FY 2004FY 2002
$300,000$300,000$300,000$300,000

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2001 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2001 cost
Personnel FTE: 1 Project Leader, 2.5 Technicians, 0.21 Administrative support $145,370
Fringe 17% of personnel costs $24,712
Supplies fish stock, etc. $15,000
Travel GSA vehicles, etc. $20,000
Indirect 26.61% $54,572
$259,654
Total estimated budget
Total FY 2001 cost$259,654
Amount anticipated from previously committed BPA funds$0
Total FY 2001 budget request$259,654
FY 2001 forecast from 2000$300,000
% change from forecast-13.4%
Reason for change in estimated budget

Budget includes cost of O&M at existing facilities only.

Reason for change in scope

Activities to establish new facilities were deleted in FY 2000.

Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
Date:
Jul 14, 2000

Comment:


Recommendation:
Fund
Date:
Sep 13, 2000

Comment:


REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$183,561 $183,561 $183,561

Sponsor comments: See comment at Council's website