Proposal title | Southern Idaho Wildlife Mitigation |
Proposal ID | 199505700 |
Organization | Idaho Department of Fish and Game AND Shoshone-Bannock Tribes (IDFG/SBT) |
Proposal contact person or principal investigator |
Name | Michele Beucler And Anders Mikkelsen |
Mailing address | P.O. Box 25 AND P.O. Box 306 Boise, ID 83707 AND Fort Hall, ID 83203 |
Phone / email | 2083342596 / [email protected] |
Manager authorizing this project | Michele Beucler AND Anders Mikkelsen |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Upper Snake / Mainstem Snake |
Short description | Protect, enhance, and maintain wildlife habitats to mitigate construction losses for Palisades, Minidoka, Anderson Ranch, and Black Canyon hydroelectric projects (a total of 52,292 unannualized HU). This project has been ongoing since 1997. |
Target species | |
Year | Accomplishment |
1997 |
Protected and/or enhanced 2,013 HU (on approx. 11,362 acres) |
1998 |
Protected and/or enhanced 6,051 HU (on 5,008 acres); Maintained above 2,013 HU |
1999 |
Protected 6,974 HU (on 2,757 acres); Maintained above 8,064 HU |
2000 |
Protect approximately 2,000 HU (on 2,450 acres; acquisition in progress); Enhance approx. 800 HU (project being developed) |
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
1. Conduct pre-acquisition activities necessary to protect 40,719 HU of wildlife habitat by 2010. This accounts for 75% of the unannualized construction losses for Palisades, Minidoka, Anderson Ranch, and Black Canyon. |
a. Identify willing landowners from whom to buy easements and/or fee-titles |
10 |
$47,336 |
|
|
b. Consult and coordinate throughout process with the NWPPC, BPA, CBFWA, Tribes, local governments, etc. |
10 |
$65,674 |
|
|
c. Complete due diligence investigations and NEPA compliance |
10 |
$62,837 |
Yes |
|
d. Seek approval from IDFG, SBT, CBFWA, BPA, etc. for program consistency |
10 |
$32,837 |
|
2. Investigate opportunities for enhancement projects on existing public lands to mitigate 14,113 HU by 2010. This accounts for 25% of the unannualized construction losses for Palisades, Minidoka, Anderson Ranch, and Black Canyon. |
a. Determine viability of proposed project |
10 |
$32,837 |
|
|
b. Determine cost-share cooperators' roles when appropriate |
10 |
$32,837 |
|
|
c. Develop MOA among partners when necessary |
10 |
$32,837 |
|
|
d.Consult and coordinate throughout process with the NWPPC, BPA, CBFWA, Tribes, local governments, etc. |
10 |
$32,837 |
|
|
e. Seek approval from IDFG, SBT, CBFWA, BPA, etc. for program consistency |
10 |
$32,837 |
|
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
1. Protect 40,719 HU of wildlife habitat by 2010 by acquiring easements or fee-title. This accounts for 75% of the unannualized construction losses for Palisades, Minidoka, Anderson Ranch, and Black Canyon. |
a. Secure fee-title and/or easement. |
10 |
$5,643,359 |
|
|
b. Complete HEP report and management plan. |
10 |
$29,947 |
|
2. Enhance 14,113 HU on protected wildlife habitat by 2010. This accounts for 25% of the remaining unannualized construction losses for Palisades, Minidoka, Anderson Ranch, and Black Canyon. |
a. Exclude livestock (or intensively manage when it can benefit wildlife) |
10 |
$3,339 |
|
|
b. Seed and/or transplant native plant species |
10 |
$3,339 |
Yes |
|
c. Manipulate water and water control structures to mimic natural water regimes |
10 |
$3,339 |
|
|
d. Remove undesirable and exotic plant species using biological, mechanical, or chemical methods |
10 |
$3,340 |
Yes |
|
e. Compare baseline with enhanced HU and credit BPA appropriate number |
10 |
$3,340 |
|
|
f. Manage public access sites to minimize human disturbance. |
10 |
$3,340 |
|
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
1. Monitor plant and animal species and communities on all properties in perpetuity and evaluate management effectiveness. |
a. Conduct baseline inventories of wildlife and plant species and communities, and develop GIS databases. |
100 |
$20,000 |
Yes |
|
b. Conduct HEPs every 5 years to quantify habitat value changes. |
100 |
$0 |
|
|
c. Conduct various wildlife surveys at regular intervals (determined by species and survey method). |
100 |
$3,487 |
Yes |
|
d. Conduct various vegetation surveys at regular intervals (determined by species and survey method). |
100 |
$3,486 |
Yes |
|
e. Continuously monitor public use. |
100 |
$1,500 |
|
|
f. Amend and update management plans. |
100 |
$2,000 |
|
Item | Note | FY 2001 cost |
Personnel |
FTE: 3.7 |
$145,090 |
Fringe |
rate varies with job titles and agencies |
$35,237 |
Supplies |
office, field, vehicle lease and repair, computers, title reports and other pre-acquisition costs |
$45,200 |
Travel |
CBFWA and Work Group coordination, training, site visits |
$26,746 |
Indirect |
approx. 28% of personnel and operating |
$83,096 |
NEPA |
cultural surveys (subcontracted) |
$15,000 |
Subcontractor |
appraisals |
$12,500 |
Subcontractor |
BPA appraisal review |
$1,500 |
Subcontractor |
environmental surveys |
$8,000 |
Subcontractor |
GIS digitizing |
$500 |
Personnel |
FTE: 1.0 |
$22,215 |
Fringe |
rate varies with job titles and agencies |
$5,065 |
Supplies |
herbicide, seed, ATV gas and repair, fence repair |
$6,080 |
Travel |
4,000 mi @ .33/mi, per diem @$100/day |
$3,320 |
Indirect |
approx 28% |
$10,914 |
Capital |
Fee-title and/or easement |
$5,636,449 |
Subcontractor |
native seed planting |
$800 |
Subcontractor |
herbicide applications |
$1,500 |
Other |
options, closing costs |
$7,000 |
Personnel |
FTE: 3.34 |
$86,503 |
Fringe |
rate varies with job titles and agencies |
$32,774 |
Supplies |
Tools and equipment, seeds for restoration, weed control and fencing supplies, vehicle leases, etc. |
$206,965 |
Travel |
Sites are located across southern Idaho |
$11,700 |
Indirect |
approx 28% |
$94,659 |
Capital |
Vehicles and motorized equipment, GPS units, storage shed, computer equipment, etc. |
$111,650 |
Subcontractor |
Agricultural equipment and services for planting permanent vegetation. |
$32,700 |
Personnel |
FTE: 0.5 (includes both IDFG and SBT personnel) |
$5,400 |
Fringe |
rate varies with job titles and agencies |
$1,782 |
Supplies |
Maps, aerial photos, GPS units, miscellaneous mensuration equipment |
$500 |
Travel |
Sites are located across southern Idaho |
$1,125 |
Indirect |
28% overhead rate |
$6,666 |
Subcontractor |
GIS services and database management assistance |
$15,000 |
| $6,673,636 |
The IDFG and SBT FY00 project proposal was ranked by CBFWA and approved by NWPPC as a Tier 1 project but received only 26% of the requested funding due to a lack of Wildlife Program funding. As a result of the 74% budget shortfall in FY00, the IDFG and SBT missed several opportunities to meet objectives (i.e., acquire fee-titles and easements). For FY01, we have kept the forecasted total from FY00 ($3.5 million) and added the difference ($3,180,546) between the FY00 approved total ($4,334,510) and the amount received ($1,153,964).
There was no change in the scope.
This information was not provided on the original proposals, but was generated during the review process.