Proposal title | Protect and Restore the Lolo Creek Watershed |
Proposal ID | 199607708 |
Organization | Nez Perce Fisheries/Watershed Program (NPT) |
Proposal contact person or principal investigator |
Name | Heidi Mcroberts |
Mailing address | P.O. Box 365 Lapwai, ID 83540 |
Phone / email | 2088437406 / [email protected] |
Manager authorizing this project | Ira Jones |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Mountain Snake / Clearwater |
Short description | Protect, restore, and enhance the Lolo Creek Watershed to provide quality habitat for chinook salmon, coho salmon, steelhead trout, pacific lamprey, and resident fish. This will be accomplished by working with an overall watershed approach. |
Target species | |
Year | Accomplishment |
1997 |
Construct 3.6 miles of fence for riparian habitat, cultural resource, and spawning habitat protection |
1997 |
Completed 12 miles of road obliteration to reduce sediment delivery to streams |
1998 |
Construction on 10 miles of riparian protection/cattle exclusion fence |
1998 |
Installation of one off-site watering development to keep cattle in the uplands and out of riparian areas |
1998 |
Completed 15 miles of road obliteration to reduce sediment delivery to streams |
1999 |
Installation of an additional off-site watering development to keep cattle in the uplands and out of riparian areas |
1999 |
Completed 20 miles of road obliteration to reduce sediment delivery to streams |
1999 |
Constructed 2 miles of riparian protection/cattle exclusion fence |
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
1. Protect and enhance critical riparian habitat as it creates fish and wildlife habitat |
a. Coordinate with the Coordinated Resource Management (CRM) group and private landowners to protect critical habitat. |
1 and on-going year-to-year |
$1,980 |
|
1. |
b. Coordinate with the Clearwater National Forest (CNF) on pre-work planning and logistics for habitat projects through a Cost-Share Agreement. |
1 and on-going year-to-year |
$1,980 |
|
1. |
c. Consult with the CNF on any NEPA, ESA consultation, or permits needed. |
1 and on-going year-to-year |
$4,979 |
|
2. Enhance bank stability within the Lolo Creek watershed, starting in the tributaries |
a. Coordinate with CRM and Potlatch Corporation to plan and implement bank stabilization projects. |
1 and on-going year-to-year |
$1,980 |
|
2. |
b. Complete any NEPA, ESA consultation, or permits needed for the project. |
1 and on-going year-to-year |
$7,646 |
|
3. Manage project to effectively accomplish project goals. |
a. Develop project time schedules. |
1 and on-going year-to-year |
$1,470 |
|
|
b. Update and communicate with the Clearwater Policy Advisory Committee and the CRM. |
1 and on-going year-to-year |
$1,470 |
|
3. |
c. Prepare quarterly and annual reports.
|
1 and on-going year-to-year |
$5,646 |
|
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
1. Protect and enhance critical riparian habitat as it creates fish and wildlife habitat. |
a. Survey culverts to be repaired or replaced. |
1 and on-going year-to-year |
$9,060 |
|
1. |
b. Replace culverts to make available critical habitat areas and/or to eliminate potential sediment problems. |
1 and on-going year-to-year |
$200,327 |
Yes |
2. Enhance bank stability within the Lolo Creek Watershed, starting in the tributaries |
a. Gather/obtain materials (logs, boulders, erosion control matting, seed) needed to complete the project. |
1 and on-going year-to-year |
$6,633 |
|
2. |
b. Implement bank stabilization. |
1 and on-going year-to-year |
$13,378 |
Yes |
3. Restore riparian plant communities to enhance fish and wildlife habitat, reduce sediment delivery to stream, stabilize banks, and improve water quality. |
a. Evaluate re-vegetation designs. |
1 and on-going year-to-year |
$1,500 |
|
3. |
b. Gather/obtain plants to be installed. |
1 and on-going year-to-year |
$5,850 |
|
3. |
c. Plant materials in riparian areas in need of habitat and stabilization. |
1 and on-going year-to-year |
$6,550 |
|
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
1. Monitor the success of excluding cattle from critical riparian areas. |
a. Collect data on the success of riparian regeneration. |
1 and on-going year-to-year |
$4,147 |
|
1. |
b. Collect data on stream characteristics which have been identified as limiting factors within this watershed. |
1 and on-going year-to-year |
$8,807 |
|
1. |
c. Analyze parameters which data collection is complete. |
1 and on-going year-to-year |
$6,520 |
|
2. Monitor and evaluate success of road obliteration practices. |
a. Collect data on vegetation growth, stabilization, and new failures. |
1 and on-going year-to-year |
$5,358 |
|
2. |
b. Conduct stream surveys to collect data related to sediment and water quality downstream from obliterated roads |
1 and on-going year-to-year |
$13,448 |
|
2. |
c. Analyze the effectiveness of road obliteration on improving stream habitat. |
1 and on-going year-to-year |
$9,414 |
|
The reason for the estimated change in budget is that through the analysis for the watershed assessment, culverts were identified as a high priority and a potential for large sediment problems in the watershed. This task is within the goals and objectives of this project, although it was not foreseeable when the FY2000 proposal were written; therefore, the funding was not projected.
This information was not provided on the original proposals, but was generated during the review process.