FY 2001 Ongoing proposal 199700900
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|
Section 1. Administrative
Proposal title | Evaluate Rebuilding the White Sturgeon Population in the Lower Snake Basin |
Proposal ID | 199700900 |
Organization | Nez Perce Tribe (NPT) |
Proposal contact person or principal investigator | |
Name | Michael A. Tuell |
Mailing address | P. O. Box 365 Lapwai, ID 83540 |
Phone / email | 2088437320 / [email protected] |
Manager authorizing this project | Silas Whitman |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Blue Mountain / Mainstem Snake |
Short description | Evaluate the need for and identify potential measures to protect and restore white sturgeon between Hells Canyon and Lower Granite dams to obtain a sustainable annual harvest of white sturgeon. |
Target species |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1996 | Upper Snake River White Sturgeon Biological Assessment |
1997 | NPT White Sturgeon Multi-Year Research Plan |
1997 | Annual report |
1998 | Annual Report |
1999 | Initiated white sturgeon telemetry study |
1999 | Initiated white sturgeon egg recovery study |
2000 | Hosted regional white sturgeon research coordination conference |
2000 | Initiated white sturgeon young-of-the-year sampling study |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
1. Evaluate the need for and identify potential actions for protecting and restoring populations to mitigate for effects of hydropower on white sturgeon productivity. | a. Conduct a biological assessment. Completed (Carmichael et. al. 1997) | 1996-1997 | $0 | |
2. Determine the status and characteristics ( reproductive and early life history of the Snake River white sturgeon population between Hells Canyon and Lower Granite Dams, including the major tributaries (Clearwater and Salmon rivers). | a. Estimate white sturgeon abundance throughout entire study area and determine if there has been any marked change in abundance or age structure of the population over the last 25 years. | 1997-2001 | $288,811 | |
b. Identify spawning behavior and movements of gravid females and mature males before, during, and after spawning. Identify spawning locations. | 1999-2002 | $14,294 | ||
c. Verify spawning activities, timing, and locations. | 1999-2002 | $18,938 | ||
d. Determine distribution/movements of fish, abundance of various age classes of white sturgeon per reach throughout the system and determine life history characteristics to be used in modeling population dynamics. | 1999-2002 | $33,142 | ||
3. Determine habitat used for spawning and rearing of white sturgeon in the Snake River between Lower Granite and Hells Canyon Dams, including major tributaries (Clearwater and Salmon Rivers). | a. Describe environmental conditions at locations where sub-adult and adult fish are captured in conjunction with tasks 1.1, 1.2, and 1.4. | 1997-2002 | $23,673 | |
4. Coordination with fisheries co-managers and funding entities and dissemination of information. | a. Attendance of regional white sturgeon technical/management meetings. | 1996-2017 | $14,115 | |
b. Data compilation and report writing. | 1996-2003 | $80,488 | ||
5. Develop an adaptive management plan. | a. Fully assess the risks associated with mitigative actions using information collected. | 2002-2003 | $0 | |
b. Make recommendations for implementation of mitigative action(s). | 2003 | $0 | ||
c. Develop an implementation, evaluation and monitoring plan. | 2003 | $0 | ||
6. Restore population to provide an annual sustainable harvest of 5 kg/ha/yr. | a. Implementation of mitigative action(s). | 2004-2014 | $0 | |
b. Evaluate and monitor effectiveness of action(s) by quantifying changes in population. | 2014-2017 | $0 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
FY 2004 | FY 2005 | FY 2002 | FY 2003 |
---|---|---|---|
$250,000 | $500,000 | $250,000 | $250,000 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2001 cost |
---|---|---|
Personnel | FTE: 8 | $243,752 |
Fringe | $55,929 | |
Supplies | $33,446 | |
Travel | $26,100 | |
Indirect | @26.6% | $95,554 |
Capital | $0 | |
NEPA | $0 | |
Subcontractor | telemetry flights | $18,680 |
$473,461 |
Total estimated budget
Total FY 2001 cost | $473,461 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2001 budget request | $473,461 |
FY 2001 forecast from 2000 | $410,000 |
% change from forecast | 15.5% |
Reason for change in estimated budget
The indirect cost for FY2001 increased 3.2% increase. A more accurate calculation of fringe resulted in a 2.8 % increase. Salary increased by 9.4% because we upgraded the field crew to technicians.
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Comment:
Comment:
Rationale: Budget increase inappropriate in this review.NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$284,350 | $0 | $0 |
Sponsor comments: See comment at Council's website