Title | Type |
---|
Section 1. Administrative
Proposal title | Wallowa County/Nez Perce Tribe Salmon Habitat Recovery Plan and Multi-species Habitat Strategy |
Proposal ID | 199702500 |
Organization | Nez Perce Tribe (NPT) |
Proposal contact person or principal investigator | |
Name | Don Bryson |
Mailing address | 612 S.W. 2nd Enterprise, OR 97828 |
Phone / email | 5414260119 / [email protected] |
Manager authorizing this project | Silas Whitman |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Blue Mountain / Grande Ronde |
Short description | Cooperative and voluntary efforts are a stated goal in the Wallowa County/Nez Perce Tribe Salmon Habitat Recovery Plan and Multi-species Habitat Strategy (County/Tribe Plan). Funding of this project will help to implement the Plan. |
Target species |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1997 | Seeded major slumps in the north part of Wallowa County following the January 1,1997 rain on snow event. |
1997 | Beak Consultants contract to develop a bull trout position paper for Wallowa County in reference to the proposed listing and for a possible countywide Habitat Conservation Plan. |
1998 | Provided funding to finalize the Lostine IFIM study and report. |
1998 | Relocated 0.36 miles of road out of the riparian zone in the Lightning Creek watershed, a tributary to the Imnaha River. |
1998 | Streambank protection and habitat improvement project on the lower Imnaha River. |
1999 | Provided cost-share to continue operation of seven mainstem flow gages in the Lostine and Wallowa rivers and Bear Creek. |
1999 | Cost-shared printing copies for peer review of updated County/Tribe Plan. |
2000 | Cost-shared purchase of duplexing color printer with OSU/ Wallowa Extension to print copies of County/Tribe Plan. This will reduce costs from $90.00/copy for commercial printing to approximately $14.00/copy. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
Promote the County/Tribe Plan at the policy level in Salem, Portland, Boise, and Washington D.C. | a. Elevate the status of the County/Tribe Plan with NMFS and USF&WS to facilitate a streamlined consultation process in Wallowa County. | 3 | $5,250 | Yes |
b. Elevate the status of the County/Tribe Plan such that it becomes the Wallowa County portion of the Oregon Plan for planning, coordination, and implementation. | 3 | $5,250 | Yes |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
FY 2003 | FY 2002 |
---|---|
$10,500 | $10,500 |
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
Provide support for the County's invasive noxious weed abatement program. | a. Provide support for the county to participate in the multi-agency effort being planned for the lower Grande Ronde corridor. | on-going | $5,000 | Yes |
Maintain and/or enhance salmon habitat and watershed conditions in Wallowa County. | Fund small projects developed through cooperative efforts between private landowners, ODF, ODFW, SWCD, NRCS, the Wallowa County NRAC, and the NPT. | on-going | $10,500 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
FY 2003 | FY 2005 | FY 2004 | FY 2002 |
---|---|---|---|
$10,250 | $10,250 | $10,250 | $10,250 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
Maintain the operation of seven mainstem flow gages in the Lostine and Wallowa rivers and Bear Creek. | Provide cost share with other entities and budgets to maintain operation of the gages. | ongoing | $21,000 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
FY 2003 | FY 2005 | FY 2004 | FY 2002 |
---|---|---|---|
$21,000 | $21,000 | $21,000 | $21,000 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2001 cost |
---|---|---|
Indirect | 5% | $500 |
Subcontractor | $10,000 | |
Supplies | Project materials such as pipe, water troughs, fencing, etc. | $10,000 |
Indirect | 5% of "supplies" line item | $500 |
Subcontractor | $5,000 | |
Indirect | 5% | $1,000 |
Subcontractor | Wallowa SWCD, OWRD, USGS | $20,000 |
$47,000 |
Total estimated budget
Total FY 2001 cost | $47,000 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2001 budget request | $47,000 |
FY 2001 forecast from 2000 | $50,000 |
% change from forecast | -6.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
REVIEW:
CBFWA Funding Recommendation
CBFWA Funding Recommendation
Recommendation:
Ongoing Funding: yes; New Funding: no
Ongoing Funding: yes; New Funding: no
Date:
Jul 14, 2000
Jul 14, 2000
Comment:
This project is tied to 199403900 and covers the M&E. This funding maintains stream gauges and other monitoring type work. The project is run through the county in order to take advantage of lower overhead costs. This is a reduced request from the FY 2001 projected budget.Comment:
Rationales: Previous commitments remain available for scope of work; Budget increase inappropriate in this review. Project has $20,000 balance from FY 2000