FY 2001 Ongoing proposal 199802100
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|
Section 1. Administrative
Proposal title | Hood River Fish Habitat Project |
Proposal ID | 199802100 |
Organization | Confederated Tribes of the Warm Springs Reservation of Oregon (CTWSRO) |
Proposal contact person or principal investigator | |
Name | Alexis Vaivoda |
Mailing address | 3430 W 10th The Dalles, OR 97058 |
Phone / email | 5412966866 / [email protected] |
Manager authorizing this project | Mick Jennings |
Review cycle | FY 2001 Ongoing |
Province / Subbasin | Columbia Gorge / Hood |
Short description | Implement habitat improvement actions that will support supplementation efforts and wild fish within the Hood River subbasin as approved by the NPPC and supported by the BPA Environmental Impact Statement for the Hood River Production Program (HRPP). |
Target species |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1996 | Completed 0.5 miles of riparian fence exclosure on Neal Creek (Kirby property). Cattle are excluded from the riparian and the riparian has been recovering. |
1996 | Completed 75 feet of bioengineered rip rap, which included vegetative plantings, on Neal Creek (Kirby property). Bank stabilized and allowed to recover. |
1998 | Completed 1.2 miles of riparian fence exclosure on Neal Creek (Guisto and Meyers property). Cattle are excluded from the riparian and the riparian has been recovering. |
1998 | Completed 75 feet of bioengineered rip rap, which included vegetative plantings, on Neal Creek (Guisto property). Bank stabilized and allowed to recover. |
1998 | Planted 130 ponderosa pine and 12 Douglas fir conifer seedlings on Neal Creek (Kirby property). Ninety percent survival through 1999. Thinned seedlings and moved to other fence enclosure locations. |
1998 | Removed a portion of the Tony Creek Dee Mill diversion concrete apron, removed stop logs, and constructed a jump pool providing access to three stream miles for spring chinook salmon, winter steelhead, bulltrout, and resident trout. |
1998 | Completed a preliminary feasibility evaluation for the East Fork Irrigation District in developing a pipe bypass system on Neal Creek. Upon construction will eliminate the need for a diversion and irrigation canal screen on Neal Creek. |
1999 | Completed 100 feet of bioengineered rip rap, which included vegetative plantings, on Neal Creek (Meyers property). Bank stabilized and allowed to recover. |
1999 | Eliminated the lower Evans Creek irrigation diversion (Higgins pond) operated by Middle Fork Irrigation District by constructing a gravity fed pressure pipe system which restored two miles of access for winter steelhead, salmon, and resident trout habitat |
1999 | Transplanted 40 Ponderosa pine (3-yr olds) from the Kirby property, planted 40 Douglas fir conifer seedlings, 200 Red Osier Dogwood, and grass seed on Neal Creek (Guisto property) for bank stabilization and riparian vegetation restoration. |
1999 | Completed 0.5 miles of riparian fence exclosure on Lenz Creek, tributary to Neal Creek (VanKoten property). Cattle are excluded from the riparian and the riparian has been recovering. |
1999 | Completed the Hood River Watershed Assessment. |
2000 | Completed the Hood River Fish Habitat Protection, Restoration, and Monitoring Plan. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|---|---|---|---|
1. Restore and recover habitat lost as a consequence of man's activities in the Hood River subbasin (see Hood River / Fifteenmile Creek Umbrella proposal 1-3, strategy g - FY 2000 process) | a. Describe habitat constraints: review watershed assessments and subbasin plans, existing biological data, land management regulations, and current production and harvest management practices. | Ongoing | $4,660 | |
1 | b. Identify habitat improvement projects; describe benefits associated with each projects; and prepare a prioritized list of habitat improvement projects from the Hood River Fish Habitat Protection, Restoration, and Monitoring Plan. | Ongoing | $5,445 | |
1 | c. Plan and develop habitat improvement projects. | Ongoing | $2,800 | |
1 | d. Implement habitat improvement projects. See subcontractors listed in the itemized estimated budget below. | Ongoing | $278,743 | Yes |
1 | e. Monitor and evaluate the physical and biological recovery associated with the habitat improvement projects. | Ongoing | $4,186 | |
1 | f. Coordination and administration oversight. | Ongoing | $4,119 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
FY 2005 | FY 2003 | FY 2004 | FY 2002 |
---|---|---|---|
$300,000 | $500,000 | $400,000 | $500,000 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2001 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2001 cost |
---|---|---|
Personnel | $7,833 | |
Fringe | @ 23% | $1,802 |
Supplies | $6,315 | |
Indirect | @ 41.4% | $6,603 |
NEPA | $3,400 | |
Subcontractor | East Fork Irrigation District (Neal Creek Invert Syphon and Lateral Canal Piping - Engineering Phase | $230,000 |
Subcontractor | Hood River Soil & Water Conservation District (HRSWCD Cost Share-Watershed/Habitat Coordinator) | $10,000 |
Subcontractor | Baldwin Creek Passage Projects (Culvert and Water Diversion Modifications) | $30,000 |
Subcontractor | Northwest Service Academy - AmeriCorp (Baldwin Creek Fencing Projects) | $4,000 |
$299,953 |
Total estimated budget
Total FY 2001 cost | $299,953 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2001 budget request | $299,953 |
FY 2001 forecast from 2000 | $300,000 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
CBFWA Funding Recommendation
Ongoing Funding: yes; New Funding: no
Jul 14, 2000
Comment:
There is no change in the budget from that estimated for FY 2001, and there is no change in the scope of work.Comment:
Rationale: Budget increase inappropriate in this review. Project expansion should be determined in provincial reviewComment:
Project just finished last week for accruals, work in September will be large, 194K in billings that not sure what has happened. Work for 04 and 05 similar to work done in previous years.Comment:
No comment submittedNW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$699,626 | $699,626 | $699,626 |
Sponsor comments: See comment at Council's website