FY 2004 Within-year Modification proposal 198331900
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|
Section 1. Administrative
Proposal title | New Marking and Monitoring Techniques for Fish |
Proposal ID | 198331900 |
Organization | National Marine Fisheries Service (NMFS) |
Proposal contact person or principal investigator | |
Name | Sandra L. Downing |
Mailing address | 2725 Montlake Blvd. East Seattle, WA 98112 |
Phone / email | 206-860-5604 / [email protected] |
Manager authorizing this project | Sandra L. Downing |
Review cycle | Within-year Modification |
Province / Subbasin | Mainstem/Systemwide / Systemwide |
Short description | |
Target species | none |
Project location
Latitude | Longitude | Description |
---|---|---|
systemwide |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
107 |
109 |
118 |
182 |
193 |
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
200102500 | Assess Current and Potential Salmonid Production in Rattlesnake Cr. Associated with Restoration Efforts | Joint project. USGS collects and analyses data obtained from the system we have installed at Rattlesnake Creek |
200262000 | Chinook Salmon Smolt Survival & Smolt to Adult Return Rate Quantification South Fork Salmon River, Idaho | System design information sharing |
199102800 | Monitoring the Migrations of Wild Snake River Spring/Summer Chinook Salmon Smolts | System design information sharing and testing of prototype equipment. This project collects and analyzes data collected at the interrogation locations. |
10120000 | Evaluation of Fish Movements Migration Patterns and Population Abundance with Stream Width PIT-Tag Interrogation Systems | System design information sharing |
Numerous other non BPA funded projects (i.e., Forest Service, Tribes, and Reclamation | System design information sharing |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|---|---|---|---|
1) Power system development | a. Oversee laboratory work by contractor | FY2004 | $3,700 | |
2) Antenna development | a. Design a shielded antenna for remote sites | FY2004 | $2,300 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1) Power system development - 100W power system | 2005 | 2005 | $30,000 |
Outyear budgets for Planning and Design phase
FY 2005 |
---|
$30,000 |
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|---|---|---|---|
1) Power system development | a. Test effects of water conductivity, water movement, water temperature, and dissolved oxygen on power production | FY2004-2005 | $14,600 | Yes |
b. Fabricate and install test power cells | FY2004-2005 | $2,000 | Yes | |
2) Antenna development | a. Fabrication of the shielded antennas | FY2004 | $4,950 | |
3) Multiplexing transceiver evaluation | a. Construct 2 improved antennas | FY2004 | $4,300 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1) Power system development - fabricate a system for in-stream work | 2006 | 2006 | $60,000 |
Outyear budgets for Construction and Implementation phase
FY 2005 | FY 2006 |
---|---|
$4,000 | $60,000 |
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|---|---|---|---|
3) Multiplexing transceiver evaluation | a. O&M of installed transceiver | FY 2004 | $6,650 | |
b. Power and access to site - landowner | FY 2004 | $750 | Yes |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|---|---|---|---|
1) Power systems development | a. Evaluate oxygen cell at Manchester. Conduct system inspections, collect performance information under various field and load conditions & test system at various conductivity, temperature, and oxygen conditions. | FY 2004-2006 | $3,400 | |
b. Evaluate effectivness of the antifouling compound under field conditions | FY 2004-2005 | $1,800 | ||
2) Antenna development | a. Evaluate effectiveness of shield on reducing EMI | FY 2004 | $9,350 | |
b. Evaluate hydraulic impact of antenna | FY 2004 | $4,700 | ||
3) Multiplexing transceiver evaluation | Evaluate the read distance, heat generation, reliability over time, and susceptability to EMI | FY 2004 | $5,800 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1) Power systems development - evaluate larger unit in field | 2005 | 2006 | $19,450 |
Outyear budgets for Monitoring and Evaluation phase
FY 2005 | FY 2006 |
---|---|
$7,450 | $12,000 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2004 cost |
---|---|---|
Personnel | FTE: 0.23 | $24,600 |
Fringe | $9,300 | |
Supplies | $8,700 | |
Travel | $3,400 | |
Capital | $2,400 | |
NEPA | subcontractor | $15,900 |
$64,300 |
Total estimated budget
Total FY 2004 cost | $64,300 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2004 budget request | $64,300 |
FY 2004 forecast from 2003 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|---|---|---|
None | $0 | cash |
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$770,000 | $508,600 | $508,600 |
Sponsor comments: See comment at Council's website