FY 2004 Within-year Modification proposal 198812025

Additional documents

TitleType

Section 1. Administrative

Proposal titleYKFP Management, Data and Habitat
Proposal ID198812025
OrganizationYakama Nation (YN)
Proposal contact person or principal investigator
NameMelvin Sampson
Mailing addressP.O. Box 151 Toppenish, WA 98948-0151
Phone / email509-865-6262 / [email protected]
Manager authorizing this projectMelvin Sampson
Review cycleWithin-year Modification
Province / SubbasinColumbia Plateau / Yakima
Short descriptionSpring and Fall Chinook, Coho and Steelhead
Target speciesSpring and Fall Chinook, Coho and Steelhead
Project location
LatitudeLongitudeDescription
Central Administrative Office 4690 SR 22, Toppenish, WA
Nelson Springs Office Complex, 771 Pence Road, Yakima, WA
Ellensburg Field Office, Ellensburg, WA
Klickitat Field Office, White Salmon, WA
O&M Upper Yakima River Supplementation Facility, Chinook Way, Cle Elum, WA
Prosser Hatchery, one mile east of Prosser, WA
Marion Drain Hatchery, ten miles southwest of Toppenish,WA
Easton Spring Chinook Acclimation Facility, Easton, WA
Clark Flat Spring Chinook Acclimation Facility, Thorp, WA
Jack Creek Spring Chinook Acclimation Facility, on North Fork of Teanaway River at confluence with Jack Creek
Easton Coho Acclimatin Facility, Easton, WA
Hatchery Slough Coho Acclimation Facility, Cle Elum, WA
Lost Creek Coho Acclimation Facility, fifteen miles northeast of Naches, WA
Stiles Pond Coho Acclimation Facility, Gleed, WA
Sharp's Pond Coho Acclimation Facility, fifteen miles south of Glenwood, WA
Roza Broodstock Collection Facility, Roza Dam on the Yakima River
Prosser Broodstock Collection Facility, Prosser Dam on the Yakima River
Chandler Juvenile Monitoring Facility, Prosser Dam on the Yakima River
Roza Juvenile Monitoring Facility, Roza Dam on the Yakima River
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA
N/A

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription
199701725 YKFP Operation and Maintenance for the Yakima River Subbasin This management proposal (198812025) supports O & M of YKFP fish production facilities in the Yakima Subbasin..
199701725 YKFP Operation and Maintenance for the Klickitat River Subbasin. This management proposal (198812025) supports O & M of YKFP fish production facilities in the Klickitat Subbasin.
198811525 YKFP Design and Construction for the Yakima River Subbasin This management proposal (198812025) supports YKFP design and construction projects/activities in the Yakima Subbasin.
198811525 YKFP Design and Construction for the Klickitat Subbasin This management proposal (198812025) supports YKFP design and construction projects/activities in the Klickitat Subbasin.
199506325 YKFP Monitoring and Evaluation for the Yakima Subbasin This management proposal (198812025) provides supports YKFP monitoring and evaluation activities in the Yakima Subbasin.
199506325 YKFP Monitoring and Evaluation for the Klickitat Subbasin This management proposal (198812025) provides supports YKFP monitoring and evaluation activities in the Klickitat Subbasin.
199506404 YKFP Policy/Technical Involvement and Planning for WDFW 199506404 provides for WDFW participation in YKFP planning and management activities. WDFW is the project sponsor.
199705600 Lower Klickitat R. Riparian and Habitat Enhancement This management proposal (198812025) provides support for 199705600, which restores, protects and enhances rearing and spawning habitat in the Lower Klickitat basin.
9705000 Little Naches Riparian and In-Channel Habitat Enhancement Enhance and restore the degraded riparian and habitat conditions in the Little Naches River by revegetating eroding banks and unstable channels, restricting vehicle traffic in the floodplain and enhancing habitat by placement of trees and boulders.
199705100 Yakima Side Channel Protect, restore, and reestablish access to productive off-channel rearing habitat, protected and reconnected floodplains associated with mainstem Yakima and Naches Rivers
9803300 Restoration of Upper Toppenish Watershed This project is designed to moderate runoff patterns in Toppenish Creek by increasing the retentiveness of natural soil water storage areas, such as floodplain and headwater meadows in the upper watershed.
199803400 Reestablish Safe Access into Tributaries of the Yakima Subbasin. Restore access to productive tributary habitats though consultation of irrigation diversion, construction of fishways and installation of screens. Protect and restore habitat through fencing and revegetation.
199901300 Ahtanum Creek Watershed Assessment Habitat restoration and monitoring in the irrigated reach of Ahtanum Creek of the Yakima Subbasin, with emphasis upon the restoration of steelhead populations
199705300 Toppenish-Simcoe Instream Flow Restoration and Assessment Habitat restoration and monitoring in irrigated reaches of Toppenish and Simcoe Creeks of the Yakima Subbasin, with emphasis upon the restoration of steelhead populations
9603501 Satus Watershed Restoration Habitat restoration and monitoring in the Satus Watershed of the Yakima Subbasin, with emphasis upon the restoration of steelhead populations
9506424 YKFP/WDFW Supplementation Monitoring Activities WDFW M & E activities related to ongoing supplementation experiments conducted by the YKFP.

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
N/A See proposal for YKFP Planning and Design objectives, tasks and budgets for Yakima Subbasin N/A N/A $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
N/A 0 0 $0
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
N/A see proposal for YKFP Construction and Implementation objectives, tasks and budgets for the Klickitat Basin N/A N/A $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
0 0 $0
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
PLEASE NOTE: Per conversation with BPA and NPPC staff, the O&M section will be used for the YKFP's Management, Data and Habitat proposal. $0
1. Provide comphrehensive management oversight of the implementation of YKFP activities. a. As YKFP Lead Agency, manage and direct YKFP mgmt, administrative, science and techinical personnel 49 $0
b. Manage and direct sub-contractors 49 $0
3. Financial Mgmt to assure compliance with contract regulations and proper accounting for contract expenditures and budgets. c. Provide and manage office space, equipment, supplies and services for YKFP personnel. The management facilities include Toppenish Complex, Nelson Springs Complex, Ellensburg Field Office and Klickitat Field Office. 49 $0
Object 1 Sub-total $30,622
8.1 Sub-Contract Policy/Legal Analyst Assist in admin/mgmt/personnel/labor, NEPA, ESA, local and state permitting requirements and general contract law. $0
8.2 Sub-contract YKFP Technical Writer Assist in development, annual revision and long term maintenance of the related documents, including master plans for each species, which track and direct eh evolution of the project. $0
Object 8 Sub-total $38,549
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1. Provide comprehensive management oversight of the implementation of YKFP activities. 2004 2007 $0
2. Support YN policy development related to YKFP activities in the Yakima and Klickitat Subbasins. 2004 2007 $0
3. Coordinate and/or perform all tasks necessary to the development of Project planning documents. 2004 2007 $0
4. Provide required administrative support for Project operations, including financial management and accountability. 2004 2007 $0
5. Design, Develop and Manage YKFP's Data and Information System. 2004 2007 $0
6. Schedule and conduct the YKFP's Project Annual Review (PAR), which includes presentations by project scientists and provides for peer review of research activities. 2004 2007 $0
7. Coordinate participation in water and habitat planning/ development initiatives by various agencies, groups and committees. 2004 2007 $0
8. Coordinate, plan and implement habitat improvement projects in the Yakima and Klickitat Subbasins. 2004 2007 $0
9. Coordinate planning and designing of construction of a coho production facility in the Yakima Subbasin. 2004 2007 $0
10. Coordinate planning and designing of construction of a steelhead production facility in the Yakima Subbasin. 2004 2007 $0
11. Coordinate planning, designing and managing construction of coho acclimation facilities in the Klickitat Subbasin. 2004 2007 $0
12. Assume management and operational responsibility for fish production activities at the Klickitat Hatchery. 2004 2007 $0
Outyear budgets for Operations and Maintenance phase
FY 2005FY 2006FY 2007FY 2008
$999,371$1,029,352$1,060,232$1,092,038

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2004 cost
Fringe $0
Supplies $24,125
Travel $1,500
Capital Indirect Cost 19.5% $4,997
NEPA Sub-Contracts $38,549
$69,171
Total estimated budget
Total FY 2004 cost$69,171
Amount anticipated from previously committed BPA funds$0
Total FY 2004 budget request$69,171
FY 2004 forecast from 2003$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$1,124,731 $1,124,731 $1,124,731

Sponsor comments: See comment at Council's website