FY 2004 Within-year Modification proposal 199602000
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|
Section 1. Administrative
Proposal title | Comparative Survival Rate Study (CSS) of Hatchery PIT Tagged Chinook & Comparative Survival Study Oversight Committee |
Proposal ID | 199602000 |
Organization | Pacific States Marine Fisheries Commission & Columbia Basin Fish & Wildlife Foundation (PSMFC & CBFWF) |
Proposal contact person or principal investigator | |
Name | Michele Dehart |
Mailing address | 2501 SW First Ave. Portland, OR 97201 |
Phone / email | 503 230 4288 / [email protected] |
Manager authorizing this project | Michele DeHart |
Review cycle | Within-year Modification |
Province / Subbasin | Mainstem/Systemwide / Systemwide |
Short description | |
Target species | Chinook & Steelhead |
Project location
Latitude | Longitude | Description |
---|---|---|
Dworshak Hatchery | ||
Pasimeroi Hatchery | ||
McCall Hatchery | ||
Rapid River Hatchery | ||
Carson Hatchery | ||
Lewiston Trap | ||
White Bird Trap, on Salmon River | ||
Grande Ronde Fish Trap | ||
Clearwater Trap |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
9.6.5.3.4. |
9.6.5.3.5 |
9.6.5.3.5.1 |
9.7.1.1 |
9.7.1.2 |
10.5.1.1 |
10.5.1.2 |
10.5.1.4 |
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
198712700 | Smolt Monitoring Program-Federal& Non-Federal | Critical Component |
199008000 | PITAGIS | Critical Component |
199403300 | Fish Passage Center | Critical Component |
19960200 | Marking Spring Chinook | Critical Component |
0 | NMFS Transportation Study (COE funded) | Critical Component |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|---|---|---|---|
1. PIT tagging at IDFG hatcheries and traps of wild and hatchery yearling chinook and steelhead in the Snake and Columbia River basins for use in the analyses of Program Objectives 1-4 (narrative). | a. steelhead tagging | $28,449 | ||
b. PIT tags | $180,000 | |||
2. PIT tagging at ODFW hatcheries and traps of wild and hatchery yearling chinook and steelhead in the Snake and Columbia River basins for use in the analyses of Program Objectives 1-4 (narrative). | a. steelhead tagging | $25,000 | ||
b. PIT tags | $45,000 | |||
3. PIT tagging at USFWS hatcheries of wild and hatchery yearling chinook and steelhead in the Snake and Columbia River basins for use in the analyses of Program Objectives 1-4 (narrative). | a. steelhead tagging - Dworshak | $18,515 | ||
b. PIT tags | $56,250 | |||
4. CSS Oversight Committee | $14,858 | |||
5. PSMFC Oversight | $1,069 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. IDFG | 2005 | 2008 | $842,590 |
2. ODFW | 2005 | 2008 | $287,729 |
3. USFWS | 2005 | 2008 | $304,784 |
4. CSS Oversight | 2005 | 2008 | $63,520 |
5. PSMFC | 2005 | 2008 | $4,472 |
Outyear budgets for Monitoring and Evaluation phase
FY 2005 | FY 2006 | FY 2007 | FY 2008 |
---|---|---|---|
$371,778 | $374,494 | $377,291 | $380,172 |
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2004 cost |
---|---|---|
Personnel | $24,586 | |
Fringe | $3,094 | |
Supplies | $13,638 | |
Travel | $19,715 | |
Indirect | PIT Tags | $281,250 |
Capital | $14,635 | |
NEPA | contractor | $12,223 |
$369,141 |
Total estimated budget
Total FY 2004 cost | $369,141 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2004 budget request | $369,141 |
FY 2004 forecast from 2003 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$828,535 | $828,535 | $828,535 |
Sponsor comments: See comment at Council's website