FY 2004 Within-year Modification proposal 199701325

Additional documents

TitleType
199701325 FY 2004 Within-year Modification, Map and Photo Narrative

Section 1. Administrative

Proposal titleYakima/Klickitat Fisheries Project Operations and Maintenance
Proposal ID199701325
OrganizationYakama Nation (YN)
Proposal contact person or principal investigator
NameMelvin R. Sampson
Mailing address151 Fort Road Toppenish, WA 98948
Phone / email(509) 865-6262 / [email protected]
Manager authorizing this projectMelvin R. Sampson
Review cycleWithin-year Modification
Province / SubbasinColumbia Plateau / Yakima
Short description
Target speciescoho, spring chinook, fall chinook
Project location
LatitudeLongitudeDescription
Ellensburg, WA Holmes Property/Acclimation Site
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA
n/a

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription
0 n/a

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
n/a $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
This request is to address a scope change only (specific task) for FY04 $0
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
n/a $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
n/a $0
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
One time only property acquisition option The negotiation and execution of an option with the property owners. (Holmes) 04 $0
NOTE: This task is estimated to cost about $30,000. The cost will be fully funded within the existing budget. The Yakama Nation will defer work to accommodate this change. No additional funding is requested at this time. $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
n/a $0
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
n/a $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
n/a $0
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2004 cost
Travel *Same as above $0
$0
Total estimated budget
Total FY 2004 cost$0
Amount anticipated from previously committed BPA funds$0
Total FY 2004 budget request$0
FY 2004 forecast from 2003$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind
n/a n/a $0 cash

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
expense
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$2,597,942 $2,597,942 $2,597,942

Sponsor comments: See comment at Council's website