FY 2004 Within-year Modification proposal 199705100

Additional documents

TitleType

Section 1. Administrative

Proposal title1997-051-00 Yakima River Side Channels
Proposal ID199705100
OrganizationYakama Nation (YN)
Proposal contact person or principal investigator
NameMelvin Sampson
Mailing addressP.O. Box 151 Toppenish, WA 98948-0151
Phone / email509-865-6262 / [email protected]
Manager authorizing this projectMelvin Sampson
Review cycleWithin-year Modification
Province / SubbasinColumbia Plateau / Yakima
Short descriptionSpring and Fall Chinook, Coho, Steelhead and Bull Trout.
Target speciesSpring and Fall Chinook, Coho, Steelhead and Bull Trout.
Project location
LatitudeLongitudeDescription
Central Administrative Office 4690 SR 22, Toppenish, WA
Nelson Springs Office Complex, 771 Pence Road, Yakima, WA
Ellensburg Field Office, Ellensburg, WA
Klickitat Field Office, White Salmon, WA
O&M Upper Yakima River Supplementation Facility, Chinook Way, Cle Elum, WA
Prosser Hatchery, one mile east of Prosser, WA
Marion Drain Hatchery, ten miles southwest of Toppenish,WA
Easton Spring Chinook Acclimation Facility, Easton, WA
Clark Flat Spring Chinook Acclimation Facility, Thorp, WA
Jack Creek Spring Chinook Acclimation Facility, on North Fork of Teanaway River at confluence with Jack Creek
Easton Coho Acclimatin Facility, Easton, WA
Hatchery Slough Coho Acclimation Facility, Cle Elum, WA
Lost Creek Coho Acclimation Facility, fifteen miles northeast of Naches, WA
Stiles Pond Coho Acclimation Facility, Gleed, WA
Sharp's Pond Coho Acclimation Facility, fifteen miles south of Glenwood, WA
Roza Broodstock Collection Facility, Roza Dam on the Yakima River
Prosser Broodstock Collection Facility, Prosser Dam on the Yakima River
Chandler Juvenile Monitoring Facility, Prosser Dam on the Yakima River
Roza Juvenile Monitoring Facility, Roza Dam on the Yakima River
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA
N/A

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription
199701725 YKFP Operation and Maintenance for the Yakima River Subbasin This proposal promotes the success of all YKFP contracts, by ensuring that habitat in priority reaches is protected and restored to maximize watershed productivity.
198811525 YKFP Design and Construction for the Yakima River Subbasin This proposal promotes the success of all YKFP contracts, by ensuring that habitat in priority reaches is protected and restored to maximize watershed productivity.
199506325 YKFP Monitoring and Evaluation for the Yakima Subbasin This proposal promotes the success of all YKFP contracts, by ensuring that habitat in priority reaches is protected and restored to maximize watershed productivity.
199506404 YKFP Policy/Technical Involvement and Planning for WDFW 199506404 provides for WDFW participation in YKFP planning and management activities. WDFW is the project sponsor.
199705000 Little Naches Riparian and In-Channel Habitat Enhancement 199705000 restores instream habitat complexity and riparian habitat function along the lower reaches of the Little Naches river.
199803300 Upper Toppenish 199803300 assesses watershed conditions for steelhead trout, and implements recommendation for passage and habitat restoration.
199803400 Reestablish Safe Access into Tributaries of the Yakima Subbasin. 199803400 strives to reconnect mainstream habitat with historically-productive tributaries.
199901300 Ahtanum Creek Watershed Assessment Habitat restoration and monitoring in the irrigated reach of Ahtanum Creek of the Yakima Subbasin, with emphasis upon the restoration of steelhead populations
199705300 Toppenish-Simcoe Instream Flow Restoration and Assessment Habitat restoration and monitoring in irrigated reaches of Toppenish and Simcoe Creeks of the Yakima Subbasin, with emphasis upon the restoration of steelhead populations
199603501 Satus Watershed Restoration Habitat restoration and monitoring in the Satus Watershed of the Yakima Subbasin, with emphasis upon the restoration of steelhead populations
199506424 YKFP/WDFW Supplementation Monitoring Activities WDFW M & E activities related to ongoing supplementation experiments conducted by the YKFP.

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
1. Idenditify Priority Stream Reaches for Project Actions. a. Coordinate with other YN staff and agency representatives to utilize available watershed assessments and professional expertise to identify priority areas. 9 $0
2. Implement informational programs in priority reaches. a. Inform affected landowners of project goals, and encourage their involvement. 6 $0
2 b. Inform and update local, state and federal land management entities of project goals and status. 6 $0
3. Plan for implementation of protection/restoration projects as they are identified. a. Develop MOU's, sale agreements, options, formal agreements with affected landowners and agencies on project scope, roles and final outcomes. 6 $0
3 b. Solicit input from WDFW and other resource managers on project plans. 6 $0
c. Collect land surveys, werland assessments and other biological reports necessary to secure permits. 6 $0 Yes
d. Conduct Environmental Land Audits, Cultural surveys, and other NEPA-related land evaluations. $0 Yes
3 e. Secure permits. $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
N/A 0 0 $0
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
Protect/Restore Critical Habitat a. Implement heavy equipment related work at Lower Nachers sites. 6 $0 Yes
b. Implement streamside and in-channel restoration actions at Hanson Ponds. 6 $0 Yes
c. Close on land and easement asquisitions, including Lower Naches Parcels (200 acres) and Plum Creek Parcel (260 acres) 6 $0
d. Coordiante activities for the implementation of acquisition and preparation to purchase. 6 $0
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Protect/Restore Critical Habitat 2004 2007 $813,683
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
1. Maintain protected status of parcels a. Pay annual property taxes, weed control, etc. 6 $94,492
1 b. Coordinate project operations to manage records of parcels and taxes. 6 $100,000 Yes
NOTE: O&M BUDGET SPLIT FROM LAND ACQUISITION PORTION UNTIL BPA DETERMINES CLASSIFICATION OF PROJECT. $0 Yes
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
1. Identify Priority Stream Reaches for Project Actions. 2004 2007 $0
2. Implement informational programs in priority reaches. 2004 2007 $0
3. Plan for implementation of protection/restoration projects as they are identified. 2004 2007 $0
Outyear budgets for Operations and Maintenance phase
FY 2005FY 2006FY 2007
$200,327$206,337$212,527

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2004 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2004 cost
Personnel FTE: 1 Habitat Biologist II $41,304
Fringe 21% $8,674
Supplies $24,720
Travel $4,375
Capital Indirect Cost 19.5% $15,419
PIT tags # of tags: Sub-Contracts $100,000
$194,492
Total estimated budget
Total FY 2004 cost$194,492
Amount anticipated from previously committed BPA funds$0
Total FY 2004 budget request$194,492
FY 2004 forecast from 2003$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

REVIEW:
NW Power and Conservation Council's FY 2006 Project Funding Review
Funding category:
capital
Date:
May 2005
FY05 NPCC start of year:FY06 NPCC staff preliminary:FY06 NPCC July draft start of year:
$0 $1,728,704 $1,728,704

Sponsor comments: See comment at Council's website