FY 2004 Within-year Modification proposal 200105500
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|
Section 1. Administrative
Proposal title | Assessment of three alternative methods of nutrient enhancement on biological communities in Columbia River tributaries |
Proposal ID | 200105500 |
Organization | National Marine Fisheries Service, Northwest Fisheries Science Center (NOAA Fisheries/NWFSC) |
Proposal contact person or principal investigator | |
Name | Beth L. Sanderson |
Mailing address | NWFSC, 2725 Montlake Blvd. East Seattle, WA 98112 |
Phone / email | (206) 860-3410 / [email protected] |
Manager authorizing this project | Dr. Beth Sanderson |
Review cycle | Within-year Modification |
Province / Subbasin | Mountain Snake / Salmon |
Short description | |
Target species | Snake River spring/summer chinook and steelhead |
Project location
Latitude | Longitude | Description |
---|---|---|
Approximately 20 streams throughout the Salmon River basin (See project proposal) |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
180 |
183 |
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
199102800 | Monitoring the Migrations of Wild Snake River Spring and Summer Chinook Salmon Smolts | Collects survival data for out-migrating juvenile chinook and steelhead |
200105500 | Shoshone-Bannock Analog Study | Collaboration- Shoshone Bannock Tribes are studying only the use of carcass analogs and no other nutrient addition methods. |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2004 cost | Subcontractor |
---|---|---|---|---|
1. Invertebrate sample processing | Send invertebrate samples collected in 2003 to invertebrate taxonomist for identification and quantification | 2004 | $42,500 | Yes |
2. Oak Ridge Laboratories (ORISE) subcontract for 8 months of field assistance (one month of salary for each of 5 undergraduate field interns , 3 months for a single returning field biologist) | Carry out baseline (pre-enhancement) monitoring fieldwork | 2004 | $27,500 | Yes |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
Additional funds for 2005 and beyond have been requested under the FY2005 budgeting request. | $0 |
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2004 cost |
---|---|---|
NEPA | Invertebrate processing subcontract $42,500 ORISE subcontract for field assistants $27,500 | $70,000 |
$70,000 |
Total estimated budget
Total FY 2004 cost | $70,000 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2004 budget request | $70,000 |
FY 2004 forecast from 2003 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$35,000 | $0 | $0 |
Sponsor comments: See comment at Council's website