FY07-09 proposal 199901700
Jump to Reviews and Recommendations
Section 1. Administrative
Proposal title | Protect and Restore Lapwai Creek Watershed |
Proposal ID | 199901700 |
Organization | Nez Perce Tribe DFRM Watershed Division |
Short description | This project will protect, restore and return critical spawning and rearing fish habitat using a ridge top to ridge top approach, based on a complete watershed assessment. |
Information transfer | Data will be housed at the Nez Perce Tribe Department of Fisheries Resource Management, Watershed Division office. Data will be submitted to StreamNet for information sharing. Data will be presented and summarized in report form and submitted to BPA. |
Proposal contact person or principal investigator |
Contacts
Contact | Organization | |
---|---|---|
Form submitter | ||
Mark D. Reaney, Jr., P.E. | Nez Perce Tribe DFRM/Watershed Div. | [email protected] |
All assigned contacts | ||
Mark D. Reaney, Jr., P.E. | Nez Perce Tribe DFRM/Watershed Div. | [email protected] |
Emmit Taylor, Jr. | Nez Perce Tribe DFRM/Watershed Div. | [email protected] |
Section 2. Locations
Province / subbasin: Mountain Snake / Clearwater
Latitude | Longitude | Waterbody | Description |
---|---|---|---|
46.2555 | -116.5971 | Lapwai Creek and it's tributaries | Lapwai Creek is a tributary to the Clearwater River, joining it 11 miles east of Lewiston, Idaho. From the confluence, main Lapwai Creek runs by the towns of Lapwai, Sweetwater, Culdesac, and Winchester. |
Section 3. Focal species
primary: Steelhead Snake River ESUsecondary: Chinook Snake River Fall ESU
secondary: Chinook Snake River Spring/Summer ESU
secondary: Coho Unspecified Population
Section 4. Past accomplishments
Year | Accomplishments |
---|---|
2005 | IMPLEMENTATION: -Ed/Outreach w/local schools -Road Erosion Report -Transportation Planning Draft -M&E fish dist., abund., comp. -3 barrier replacement designs -Culvert design estimating spreadsheet -2 mi.fence -80 ac. weed control -NRAMP 10 parce |
2004 | IMPLEMENTATION: -Coord. w/ NRCS, NPCSWCD, NPT Water Resources -Planted 5 acres of vegetation -60 acres of weed control -Ed/Outreach -Fish Barrier Assessment -M&E fish distribution, abundance, composition PLANNED: -3.5 mi. wetland/riparian fencing |
2003 | IMPLEMENTATION: -Survey stream crossings -surveyed roads for erosion potential -Prioritize fish barrier projects -Planted 3 acres of vegetation -Collaborated landowners, NRCS, and NPSWCD -Analyze CY2002 biol., chem., and habitat data |
2002 | IMPLEMENTATION: -Compiled road maps, obtained landowner permission to survey roads -Provided fish passage survey training -Surveyed stream crossings -4 miles of riparian/ wetland fencing -M&E fish distribution, abundance, etc. -Coordinated |
2001 | Planned - Survey of all roads within Nez Perce Tribal lands for watershed restoration opportunities Planned - Final Lapwai Creek Watershed Assessment Document |
2000 | Field Check of Watershed Assessment Data 85% of the allocated budget was used to begin a required Clearwater Subbasin Assessment and Plan |
1999 | Draft Lapwai Creek Watershed Assessment |
Section 5. Relationships to other projects
Funding source | Related ID | Related title | Relationship |
---|---|---|---|
BPA | 199706000 | Clearwater Focus Watershed Program; NPT | This project implements the goals and objectives of this program. |
BPA | 199608600 | Clearwater Focus Program-IDSCC | This project implements the goals and objectives of this program. |
BPA | 198335003 | Nez Perce Tribal Hatchery M&E | Protection and restoration of fisheries habitat and water quality for fall chinook and coho satelite facility 0.8 miles upstream on Lapwai Creek from confluence with Clearwater River. |
BPA | 200207000 | Lapwai Cr Anadromous Habitat | This project focuses on habitat restoration and protection implementation on tribal properites and compliments project 200207000 which implements BMPs on private lands to reduce sediment, nutrients, and stream temperature, and improves low summer flows. |
Other: Region 10 EPA | n/a | NPT Water Resources Wetland Program Development Grant | This project works cooperatively with the NPT Water Resources Division to assess , protect and restore wetlands and water quality. |
BPA | 198335000 | Nez Perce Tribal Hatchery O&M | This project compliments the hatchery supplementation to restore and recover Snake River Basin salmon stocks by improving habitat quantity/quality. |
Section 6. Biological objectives
Biological objectives | Full description | Associated subbasin plan | Strategy |
---|---|---|---|
Biological Problem 2, Objective B. | Improve anadromous fish productivety and production, and life stage specific survival through habitat improvement. | Clearwater | 1. Identify and prioritze primary limiting factors. 2. Evaluate alternative habitat treatments to address limiting factors. 4. Develop indicies to evaluate biological response to habitat improvement. 5. Implement projects following priotization. 7. M&E. |
Environmental Problem 10, Objective BB. | Protect and restore an additional 300 miles of riparian habitats by 2017. | Clearwater | 1. Strategy: Identify and prioritize riparian habitats for protection and restoration. 2. Strategy: Protect and restore riparian habitats through....conservation easements, land exchanges, promotion of BMPs and alternative grazing strategies.. |
Environmental Problem 10, Objective BB. | Protect the existing quality, quantity and diversity of native plant communities providing habitat to native wildlife species by preventing the introduction, reproduction, and spread of noxious weeds and invasive exotic plants into and within the subbasin | Clearwater | 1. Strategy: Identify and prioritize native plant communities for protection from exotic weeds. 2. Prevent reproduction... 3. ..encourage use of weed free seeds and feeds. 5. Increase public participation - develop education and awareness programs. |
Environmental Problem 10, Objective Z. | Protect all currently functioning wetlands. | Clearwater | 2. Strategy: Protect wetland habitats through ... conservation easements .... public education, promotion of BMPs, promotion of alternative grazing strategies. 3. Strategy: Continue effective activities--continue existing programs ..... |
Environmental Problem 11, Objective CC. | The introduction of noxious weeds and nonnative plant species into the Clearwater subbasin has negatively impacted native terrestrial focal species. | Clearwater | 1. Identify ans prioritize native plant communities for protection from exotic weeds. 3. Encourage the use of weed free seeds and feeds. 5. Increase public participation through education and awareness programs. 6. Prevent establishment of new invaders.. |
Environmental Problem 11, Objective DD. | Reduce the extent and density of noxious weeds | Clearwater | 1. Prioritize for treatment - identify and prioritize noxious weed infestations for treatment. 2. Treat Weed infestations - implement methods for reducing weed densities. 3. Encourage best practices- 4. Monitor and evaluate efforts to reduce weeds. |
Environmental Problem 12, Objective EE. | Reduce the negative impacts of livestock grazing on fish, wildlife and plant poulations in the watershed. | Clearwater | 1. Identify and prioritize areas impacted by grazing for protection and restoration. 2. Reduce grazing impacts--encourage establishment of riparian pasture, exclusion fences, off-site watering, or riparian conservation easments (Lease Land) |
Environmental Problem 12, Objective FF. | Reduce conflicts between livestock and native wildlife and plant populations. | Clearwater | 4. Reduce cattle/elk conflicts--where possible, alter grazing management to minimize cattle/elk conflicts, especially on elk winter range areas. 5. Monitor and evaluate efforts to reduce impacts of cattle on plant and wildlife species. |
Environmental Problem 16, Objective JJ | Reduce the impact of the transportation system on wildlife and fish populations and habitats | Clearwater | Reduce road impacts--implement road closures and decommissioning programs in areas identified in the assessment and Section 4.4 to have high road densities, high sediment production, high surface erosion, and/or landslide prone. Prioritize areas with..... |
Environmental Problem 7, Objective P. | Reduce number of artificially blocked streams by 2017 | Clearwater | Remove or modify human-caused barriers--emphasize alteration/removal of unatural barriers over natural barriers. |
Environmental Problem 7, Objective Q. | Reduce water temperature to levels meeting applicable water quality standards for life stage specific needs of anadromous and native resident fish, with an established upward trend in the number of stream miles meeting standards by 2017. | Clearwater | 3. Restore riparian functions related to temperature--continue efforts aimed at increasing streamside shading where shading has been removed by anthropogenic activities.....Restore watershed functions impacting temperatures. |
Environmental Problem 7, Objective S. | Reduce instream edimentation to levels meeting applicable water quality standards and measures, with an established upward trend in the number of stream miles meeting such criterion by 2017. | Clearwater | 4.Reduce sediment--reduce sediment inputs by implementing practices that address problems from logging, mining agricultur and other historic and current sediment producing activities. This work item includes upgrades to road surface and drainage features. |
Environmental Problem 7, Objective T. | Develop a nutrient allocation plan for the subbasin which investigates the potential benefits to fish and wildlife of nutrient additions or reductions. | Clearwater | 1. Inventory and map all potential anthropogenic nutrient inputs including waste water treatment facilities, industrial sources, feedlots, and non-point sources. Define nutrient poor or rich stream reaches throughout the basin. |
Environmental Problem 7, Objective U. | Improve aquatic habitat diversity and complexity to levels consistent with other objectives outlined in this document, with particular emphasis on recovery of anadromous and fluvial stocks | Clearwater | 1. Identify the need--identify habitats that have been simplified to a degree detrimental to anadromous and residential populations. 2. Follow Existing Plans..3. Prioritize Actions...4. Restore complexity...5. Restore ecosystem function.. |
Socioeconomic Problem 18, Objective LL. | Develop programs and project proposals compatible with existing community needs and that integrate with local watershed protection, restoration and management objectives and activities. | Clearwater | 1. Involve communities and finer scale efforts in subbasin planning and project planning. 2. Coordinate plan implementation with federal, state, tribal, local to avoid program and project duplication. 3. Seek formal local support for programs/projects. |
Socioeconomic Problem 18, Objective LL. | Identify high priority habitat areas requiring protection or restoration. | Clearwater | 1. Develop a prioritization process to achieve multiple objectives, values, and benefits. 2. Integrate prioritization processes to increase the comprehensiveness of criteria considered, and to increase the strategic effectiveness of programs/projects. |
Socioeconomic Problem 21, Objective PP. | Participate in existing, and contribute to the further development of, local watershed and technical advisory groups. | Clearwater | Assist NPSWCD and the WAG and other existing groups to organize project goals and implementation strategies. 2. Assist interested groups with organizing local watershed programs. 3. Facilitate networking of these groupswith technical assistance... |
Socioeconomic Problem 21, Objective QQ. | Maximize social and economic benefits as much as possible while implementing the Clearwater Subbasin Plan. | Clearwater | 1. Maximize economic benefits of plan--for land purchases or easements, efforts should be made to minimize loss of local government revenues. 2. Efforts should be made to utilize local labor forces, contractors, and suppliers when implementing habitat i |
Socioeconomic Problem 21, Objective RR. | Increase resource information and education delivery in the subbasin. | Clearwater | 1. Promote ridgetop to ridgetop stewardship of natural resources through enhanced local involvement and support. 2. Implement information/education activities identified in subbasin plan. 3. Provide information/assistance to NPSWCD. 4. Provide opport... |
Terrestrial Problem 6, Objective M. | Increase understanding of the composition, population trends, and habitat requirements of the terrestrial communities of the Clearwater. | Clearwater | 1. Collect data--develop a subbasin-wide survey program and database for terrestrial focal, ESA listed, neotropical migrant, and culturally important species. 2. Increase documentation - supoport the efforts of the Idaho Conservation Data Center (CDC) |
Section 7. Work elements (coming back to this)
Work element name | Work element title | Description | Start date | End date | Est budget |
---|---|---|---|---|---|
Manage and Administer Projects | Construction Project Management, Coordination and Communication | Project Mangement includes coordinating project activities, attending meetings, seeking additional funding, preparing statements of work, managing budgets, completing reports and responding to BPA requests. | 3/1/2007 | 2/28/2010 | $103,529 |
Biological objectives Environmental Problem 7, Objective S. Environmental Problem 7, Objective U. |
Metrics |
||||
Coordination | Coordination with federal, tribal, state, local and other interests | Coordination with federal, tribal, state, local and other interests to avoid program and project duplication, increase cooperation/collaboration, coordinate efforts and education and outreach goals. Involve the community in project planning and implementation including the completion of public meetings for local input and involvement. | 3/1/2007 | 2/28/2010 | $49,594 |
Biological objectives Socioeconomic Problem 18, Objective LL. |
Metrics |
||||
Provide Technical Review | Technical Assistance to NPSWCD, NPT Natural Resources-Water Resources and Forestry Divisions and NP County Road & Bridge Dept. | Technical Assistance to NPSWCD, NPT Natural Resources-Water Resources and Forestry Divisions and NP County Road & Bridge Dept. with design, consultation, technical review of project plans and implementation. | 3/1/2007 | 2/28/2010 | $38,068 |
Biological objectives |
Metrics |
||||
Create/Manage/Maintain Database | Maintain project installation database | Develop and update database and GIS layers to track project installation location and project specific information over time. This database will be in coordination with the NPWSCD and shared with other agencies as well as BPA's annual RPA reporting. | 3/1/2007 | 2/28/2010 | $35,998 |
Biological objectives Environmental Problem 7, Objective S. |
Metrics |
||||
Produce Status Report | Quarterly Reports To BPA | Produce Status Reports/Pisces | 3/1/2007 | 2/28/2010 | $28,228 |
Biological objectives |
Metrics |
||||
Produce Annual Report | Produce Annual Report | Annual report describes all yearly activities, successes and problems encountered including photos and data collected summarized. | 3/1/2007 | 2/28/2010 | $27,390 |
Biological objectives |
Metrics |
||||
Produce Inventory or Assessment | NPT Natural Resource Assessment and Management Plan (NRAMP) | Conduct NRAMP surveys of 10 individual tribal properties per year, assessing stream and management activities. Produce restoration project recommendations utilizing an IDT team. This work element is the primary basis for identifying restoration actions. | 3/1/2007 | 2/28/2010 | $179,538 |
Biological objectives Biological Problem 2, Objective B. |
Metrics |
||||
Produce Design and/or Specifications | Prepare Engineering & Technical Designs for Restoration Projects | Complete surveys to obtain site specific data for the completion of engineering and technical designs. This work includes, but is not limited to, cross-sections, benchmark elevation determination, topographic and photometric surveys. Design package includes surveys, engineering or technical drawings, site maps, construction or installation specifications and material specifications, and cost-estimates. A list of projects is developed each Fall following the filed season and then designs are prepared through the Winter for the highest priority projects. Designs are completed through a coordinated team of professionals including NPSWCD, Nez Perce County Road & Bridge Dept., local Highway Districts, Idaho Department of Fish & Game, and others. | 3/1/2007 | 2/28/2010 | $60,054 |
Biological objectives |
Metrics |
||||
Produce Environmental Compliance Documentation | Landowner Approval, NEPA, ESA and Cultural Resource Compliance | Secure landowner approval for restoration action implementation. Landowner approval will be from the Nez Perce Tribe, Tribal Allotment owners and BIA. Produce Environmental Compliance documentation for review and approval for all on-the-ground implementation projects and actions. NEPA will occur through BPA's NEPA process checklist and ESA compliance through BPA's HIP BiOp process. Cultural resource surveys and compliance will be contracted to the Nez Perce Cultural Resources Department. In addition, NEPA will be completed through the NPT's process. | 3/1/2007 | 2/28/2010 | $37,295 |
Biological objectives Environmental Problem 7, Objective S. Environmental Problem 7, Objective U. |
Metrics |
||||
Install Fish Passage Structure | Replace Fish Passage Barrier Structures w/ Alternative Funding Sources | Replace barrier culverts with fish friendly structures as recommended and prioritzed by IDT team, Fish Barrier Assessment and NRAMP . Implementation items will include advertisement for bid of on-the-shelf designs, site inspection, bid award and notification, contract management and administration, final inspection, and implementation monitoring. This work item will be a cost-share item to compliment grant funding from other sources for construction contracts. Target is to replace 2 structures per year in 2007, 2008 and 2009. This work item will be used as cost-share with alternative funding. | 7/15/2007 | 11/1/2009 | $48,063 |
Biological objectives Biological Problem 2, Objective B. |
Metrics * Does the structure remove or replace a fish passage barrier?: Yes * Was barrier Full or Partial?: Full * # of miles of habitat accessed: based on prioritized replacement strategies |
||||
Develop Alternative Water Source | Create Alternative Water Source for Livestock | Where livestock water directly from stream sources or springs, alternative water sources will be developed. These water sources include wind, solar and gravity fed systems. Typical components of a water system include a trough and pipeline. Target is to construct 2 off-site watering structures per year in 2007, 2008 and 2009. | 3/1/2007 | 12/1/2009 | $36,854 |
Biological objectives Environmental Problem 10, Objective Z. Environmental Problem 12, Objective EE. Environmental Problem 7, Objective U. Socioeconomic Problem 21, Objective QQ. |
Metrics |
||||
Install Fence | Install Fence to Protect Wetlands/Riparian Areas | Install riparian protection fencing as recommended by NRAMP. Work items include prepare materials list, order and aqcuire materials, install fence using NPT Fencing Crew. Target is to construct 1 miles of fence per year in 2007, 2008, and 2009 protecting 0.5 mile of stream. | 3/1/2007 | 2/28/2010 | $44,410 |
Biological objectives Environmental Problem 12, Objective EE. |
Metrics * # of miles of fence: 2 |
||||
Remove vegetation | Treat Exotic Invasive Plant Species | Implement invasive weed treatment methods before planting as recommended by NRAMP, for reducing weed densities and competition to assist the establishment of native plant communities. Treatments will be completed by mechanical (pulling or by weed eaters) or chemical means. Target is to treat 10 acres per year in 2007, 2008, and 2009. This work element is directly related to the "Plant 10 acres of vegetation per year" work element below. Work will be completed by the Idaho Department of Corrections Prision Crew. | 5/1/2007 | 7/31/2009 | $42,788 |
Biological objectives Environmental Problem 11, Objective CC. Environmental Problem 11, Objective DD. |
Metrics * # of acres treated: target is to treat 10 acres per year |
||||
Plant Vegetation | Plant 5 Acres of Vegetation per year | Plant vegetation in riparian areas recommended by NRAMP to increase stream shading and habitat diversity and complexity. Trees, shrubs and grasses include only native species and will be certified weed-free. Target is to plant 5 acres of riparian buffer vegatation per year in 2007, 2008 and 2009. | 3/1/2007 | 2/28/2010 | $41,829 |
Biological objectives Environmental Problem 7, Objective Q. |
Metrics * # of acres of planted: 10.0 |
||||
Lease Land | Lease Tribal Grazing Lands | Lease tribal grazing allotments as they expire using alternative sources of funding to eliminate livestock grazing. This work element is for the anticipated cost-share used with other funding sources. | 3/1/2007 | 2/28/2010 | $25,703 |
Biological objectives Environmental Problem 10, Objective BB. Environmental Problem 10, Objective Z. Environmental Problem 11, Objective DD. Environmental Problem 12, Objective EE. Environmental Problem 12, Objective FF. Environmental Problem 7, Objective Q. Environmental Problem 7, Objective U. |
Metrics * # of acres of new lease: 500 acres/year |
||||
Upland Erosion and Sedimentation Control | Install Upland Erosion and Sediment Control w/ alternative funding sources | Implement erosion control measures such as grassed waterway, terraces, and buffers as recommended by NRAMP and utilizing alternative funding sources, to reduce or prevent sediment from reaching the stream. The target is to implement practice on 1 mile of stream per year in 2007, 2008 and 2009. | 6/1/2007 | 12/1/2009 | $20,478 |
Biological objectives Environmental Problem 7, Objective S. |
Metrics * # of acres treated: 10.0 |
||||
Create, Restore, and/or Enhance Wetland | Restore and Enhance Wetlands | Implement wetland restoration and enhancement measures as recommended by NRAMP. Target is to restore or enhance 3 acres of wetland per year in 2007, 2008 and 2009. | 3/1/2007 | 2/28/2010 | $20,106 |
Biological objectives Environmental Problem 10, Objective Z. |
Metrics * # of acres treated: 3.0 acres target per year |
||||
Produce Design and/or Specifications | Bid Package and Contract Development for Road Decommissioning and Improvements | Produce bid packages and contract documents for 5 miles of road decommissioning and 0.5 mile of road improvement projects each year. | 3/1/2007 | 12/31/2009 | $38,275 |
Biological objectives Environmental Problem 16, Objective JJ Environmental Problem 7, Objective S. |
Metrics |
||||
Decommission Road | Decommission 5 miles of Road Per Year | Decommission 5 miles of forest road per year. Work items include contract administration and site inspection. | 6/1/2007 | 9/30/2009 | $67,288 |
Biological objectives Biological Problem 2, Objective B. Environmental Problem 16, Objective JJ Environmental Problem 7, Objective S. |
Metrics * Type of decommissioning: Recontoured * # of road miles decommissioned : 10.0 miles per year |
||||
Plant Vegetation | Road Decommissioning: Planting/Revegetation | All decommissioned roads will be revegetated with native grass seed and vegetation. | 6/1/2007 | 10/1/2009 | $23,106 |
Biological objectives Environmental Problem 7, Objective Q. |
Metrics * # of acres of planted: 50.0 acres |
||||
Improve/Relocate Road | Improve 0.5 mile of road per year | Improve permanent roads, as specified by 2005 Transportation Plan, by upgrading cross section to a 14' width, with 2" of crushed gravel driving surface and an adequate roadside drainage ditch. Improvements include upgrading cross section and ditch, addition of base and surface aggregates and upgrading inadequate cross drains to reduce erosion from entering the streams. | 5/1/2007 | 10/31/2009 | $101,406 |
Biological objectives Biological Problem 2, Objective B. Environmental Problem 16, Objective JJ Environmental Problem 7, Objective S. |
Metrics * # of road miles improved, upgraded, or restored: 1.0 miles per year |
||||
Maintain Vegetation | Maintain Riparian Vegetation Planted in Previous Years | Maintenance of vegetation planted by controlling noxious invasive weeds. Weed control methods include one or a combination of mechanical (pulling or mowing) herbicide (spot spraying) or biological means as recommended by NRAMP. Target is to implement 60 acres of weed control per year in 2007, 2008 and 2009. Control will be completed by a combination of prision and tribal crews. | 5/1/2007 | 10/31/2009 | $25,238 |
Biological objectives Environmental Problem 7, Objective Q. Environmental Problem 7, Objective S. Environmental Problem 7, Objective U. Socioeconomic Problem 21, Objective QQ. |
Metrics |
||||
Operate and Maintain Habitat/Passage | Maintain Previous Years Fence Construction | Maintain previously constructed fence. Maintanence is required to ensure a properly functioning fence that protects riparian and stream habitat. Target is to maintain approximately 15 miles of fence per year. | 3/1/2007 | 2/28/2010 | $29,211 |
Biological objectives Environmental Problem 10, Objective Z. Environmental Problem 7, Objective Q. Environmental Problem 7, Objective S. Socioeconomic Problem 21, Objective QQ. |
Metrics |
||||
Collect/Generate/Validate Field and Lab Data | Project Compliance and Implementation Monitoring | Post project monitoring to ensure project specifications were completed. Set up and collect data to evaluate restoration projects to ensure desired outcomes are met. Data collection may include photo points, vegetation plots, cross-sections and post year site inspections. | 3/1/2007 | 12/30/2009 | $23,727 |
Biological objectives |
Metrics |
||||
Analyze/Interpret Data | Analyze Project Compliance and Implementation Monitoring Data | Analyze project compliance and implementation monitoring data to ensure projects are meeting desired outcomes. Additional work and lessons learned will be incorporated into NRAMP plans. | 3/1/2007 | 12/31/2009 | $14,788 |
Biological objectives |
Metrics |
||||
Outreach and Education | Outreach and Education | Provide project specific and general fish habitat protection and restoration information to the public through local news papers, school news letters, radio announcements, public awareness meetings, billboards and educational presentations at the local schools. | 3/1/2007 | 2/28/2010 | $40,044 |
Biological objectives Environmental Problem 7, Objective S. Socioeconomic Problem 21, Objective RR. |
Metrics * # of teachers reached: 10 * # of general public reached: 1000 * # of students reached: 500 |
Section 8. Budgets
Itemized estimated budget
Item | Note | FY07 | FY08 | FY09 |
---|---|---|---|---|
Personnel | Project Leader, Engineer - FTE, Plant/Wetland Biologist, Tech II-1/2 FTE | $154,102 | $163,348 | $173,149 |
Fringe Benefits | 30% Full Time; 15% Tax-free full time; 10% Temp | $46,231 | $49,004 | $51,945 |
Supplies | Field and Office Supplies, Repairs | $1,800 | $1,800 | $1,800 |
Travel | Training Travel/Per Diem | $10,195 | $10,195 | $10,195 |
Overhead | 29.64% Admin. Overhead | $75,183 | $77,147 | $80,923 |
Supplies | Fencing/Planting/NRAMP Supplies, Materials & Hardware | $17,030 | $15,635 | $15,635 |
Overhead | GSA Vehicle Rent | $12,645 | $12,645 | $12,645 |
Overhead | Office Rent | $683 | $683 | $683 |
Other | Training Conferences/Workshops (tba) | $4,107 | $4,107 | $4,107 |
Other | Repairs & Maintenance | $775 | $775 | $775 |
Other | Mobile Phones for Field Crews | $520 | $520 | $520 |
Other | Computer Services | $6,250 | $2,250 | $2,250 |
Other | Consultants/Contracts | $60,250 | $60,250 | $60,250 |
Totals | $389,767 | $398,357 | $414,875 |
Total estimated FY 2007-2009 budgets
Total itemized budget: | $1,202,999 |
Total work element budget: | $1,203,005 |
Cost sharing
Funding source/org | Item or service provided | FY 07 est value ($) | FY 08 est value ($) | FY 09 est value ($) | Cash or in-kind? | Status |
---|---|---|---|---|---|---|
Idaho Soil & Conservation Commission | In cooperation with NPSWCD, engineering design assistance | $5,000 | $5,000 | $5,000 | In-Kind | Confirmed |
Idaho Transportation Department | Include Fish Friendly Designs in all future Hwy Improvement Projects in the Watershed, | $5,000 | $5,000 | $5,000 | In-Kind | Confirmed |
Local Hwy Districts, LHTAC | Culvert Upgrades projects to incorporate fish friendly designs, only | $2,500 | $2,500 | $2,500 | In-Kind | Confirmed |
Nez Perce County Road & Bridge Department | Design Reviews, Permenant Signing, Traffic Control Plans, Construction Inspection, NPDES Plans | $4,251 | $4,506 | $4,776 | In-Kind | Confirmed |
NPSWCD | Coordination, Land Owner Education, Project Oversight, Design Assistance and Review | $15,225 | $16,139 | $17,107 | In-Kind | Confirmed |
NPSWCD | Landowner Relationship Building Assistance, Negotiating of Property entry permission | $1,500 | $1,500 | $1,500 | In-Kind | Confirmed |
NPT Natural Resources- Forestry Division | Assstance with Transportation Planning, road maintenace recommendations, consultations | $3,000 | $3,000 | $3,000 | In-Kind | Confirmed |
NPT Natural Resources-Land Services Division | GIS Data Base data, training, consulting, map printing | $12,500 | $12,500 | $12,500 | In-Kind | Confirmed |
NPT Natural Resources-Water Resources Division | Water Quality Monitoring and Consultation | $20,000 | $20,000 | $20,000 | In-Kind | Confirmed |
PL 566 | In cooperation with NPSWCD, technical assistance and BMP installation cost-share (cash & in-kind) | $10,000 | $10,000 | $10,000 | In-Kind | Confirmed |
Totals | $78,976 | $80,145 | $81,383 |
Section 9. Project future
FY 2010 estimated budget: $685,329 FY 2011 estimated budget: $685,329 |
Comments: Implemetation of Protection and Restoration BMP's |
Future O&M costs: Following completion of Fish Passage Assessment, Road Erosion Survey and Assessment, NRAMP & SVAP Habitat Assessments, M&E Fish Distribution, Abundance, and Composition Data Collection, and other studies and assessments, the NPT wiil have a full prioritized list of Protection and Restoration implementation projects that will require increases in funding to achieve increased fish populations. Other anticipated work elements include: Annual fence maintenance; Annual Weed Control; Annual Implementation Monitoring
Termination date: None
Comments: Since begining this project, the NPT Fisheries Watershed Division has completed Road Erosion Surveys, Fish Barrier Assessments, Watershed Assessments, etc., throughout the watershed. We are now in an implementation based phase of this project and this proposal includes increased funding associated with implementation.
Final deliverables: Lapwai Creek and it's tributary watersheds will be intact, healthy, and properly functioning so that they are able to support all native anadromous and resident fish species at historical or near-historical levels. Streams within the watershed will meet TMDL and Nez Perce Tribal DFRM Watershed standards.
Section 10. Narrative and other documents
NPT Watershed Div. response to ISRP Comments | Jul 2006 |
Revised Narrative | Jul 2006 |
NPT DFRM Watershed Umbrella Comments | Jul 2006 |
Mtn Snake NPT DFRM Project Recommendations with comments | Jul 2006 |
199901700 Proposal: Fix-It-Loop Version | Nov 2006 |
199901700 Proposal: Fix-It-Loop Version | Nov 2006 |
Reviews and recommendations
FY07 budget | FY08 budget | FY09 budget | Total budget | Type | Category | Recommendation |
---|---|---|---|---|---|---|
NPCC FINAL FUNDING RECOMMENDATIONS (Oct 23, 2006) [full Council recs] | ||||||
$389,765 | $389,765 | $389,765 | $1,169,295 | Expense | ProvinceExpense | Fund |
NPCC DRAFT FUNDING RECOMMENDATIONS (Sep 15, 2006) [full Council recs] | ||||||
$389,765 | $389,765 | $389,765 | $0 | ProvinceExpense | ||
Comments: ISRP fundable in part. Funding in FY 2007 to complete reports on abundance, habitat status and a comprehensive presentation of prioritized restoration projects. Funding for restoration actions in 08 and 09 is conditioned on favorable ISRP and Council review of revised proposal linked to completed reports (per ISRP comments) |
ISRP PRELIMINARY REVIEW (Jun 2, 2006)
Recommendation: Response requested
NPCC comments: Proposals 199901700 (NPT - Protect and Restore Lapwai Creek Watershed) and 200207000 (NPSWCD - Lapwai Creek Anadromous Habitat) are for companion projects on the same creek (Lapwai) for activities on NPT tribal lands (199901700) or private ranch lands (200207000). They use the same format for the entire proposal and much of the text is copied verbatim in each proposal. Despite previous positive reviews, the ISRP is becoming concerned. Between this and its sister SWCD project, many millions have been spent over the past 7 years and there is no end in sight. Project accomplishments are so minimal that the two projects should not be continued without a thorough programmatic review. Such a review is recommended as a condition of future funding. The response requested here is to produce a revised proposal that addresses the problems identified in this assessment and to include responses to requests for additional information, and incorporates the recommended changes in structure. The on-the-ground work here may have potential of producing measurable results, but there still is no comprehensive assessment and prioritized prescriptions, nor evidence of a fish response from accomplishments to date, nor plans to provide such evidence. In general the proposal is difficult to follow; the organization does not efficiently communicate the historic and contemporary status of the focal species, the historic and contemporary status of the habitat, or the desired future state of the ecosystem (habitat) or the focal species. There are general statements on the status of each of these elements, but not specific detail. Because the detail is not present it is not possible to evaluate the reasonableness of the proposal. Simultaneous with a lack of sufficient detail is considerable redundancy of general statements. This creates a proposal that is too long and difficult to follow. For example, in spite of presenting a 12-page Technical and Scientific Background, the sponsors never report how many kilometers/miles of streams exist in the watershed, broken down by the main creek and tributaries. They never identify which tributaries and reaches are believed to be the historic production areas, which are currently producing fish, and which are believed to be essential for achieving the production needed to be "recovered." This section needs a brief one-paragraph description of the stream system. Including the kilometers of stream by tributary. A brief summary of the watershed assessments and how they form the basis for the proposal should be provided. These are given in the existing proposal, but the evaluation is overly vague -- summer low flow, sediment, etc. are problems. The summary of the watershed assessments should identify a priority list of stream segments that have degraded ecosystem functions and identify the management actions that will be used to remedy these altered conditions. The sponsors could identify important stream reaches for protection and restoration on maps. The sponsors have completed a road assessment and a barrier assessment, but the recommendations from these assessments are not communicated in the technical background. How many barriers are there, which are believed critical to gaining access to productive habitat? Where is road condition worst? Where is it recommended to begin road decommissioning and renovation? Some of this is buried in the work elements - it needs to be in the technical section. The technical section should not exceed 5 pages (could be 3 or 4). The Rationale and Significance to Subbasin Plans section is too long and ineffective. It should be reduced to no more than 2 pages. There is a bulleted list of justifications for Lapwai Creek watershed restoration. Most of these may not in fact be adequate justification. For example - " …presence of at-risk wild A-run steelhead" is justification only if this is a core remnant population essential for recovery identified in the interior Columbia Basin TRT independent population reports and the updated NOAA status review for steelhead. From what is presented it is not clear that this stream is particularly important. Lapwai/Sweetwater creeks were identified by NOAA BIOP (draft) as the historical source population for A-run steelhead in the Lower Clearwater Basin. This is justification only if these creeks are still likely to serve as the contemporary and future source population for A-run steelhead in the Lower Clearwater. Clear evidence from the Clearwater subbasin plan is needed that the focal species of this project are identified as focal species, that the strategies for restoration are consistent with the plan, and that the Lapwai Creek and tributaries are identified as a priority area. This should only require a short paragraph and table. Clear evidence is also needed to show Lapwai Creek is identified in federal recovery documents (the TRT independent population report, steelhead status review, and possibly the hydrosystem BiOp). Identifying every element of the subbasin plan that may apply to these proposals, and identifying every BiOp RPA that may apply is a distraction and does not serve to communicate how this proposal will serve to fulfill the obligations of the Council's Fish and Wildlife Program or the ESA recovery actions. The section of the Mission-Lapwai Creek Watershed plan produced in 1990 and updated in 1994 and 2000 needs clarification. It simply restates what has been said over and over again in the proposal, "… improve flow, enhance riparian, and reduce sediment." The priority locations recommended by this plan need to be identified and tied to specific objectives in the proposal. There are lists of accomplishments, but there are no management implications identified. No data on fish abundance are provided. This appears to be the only accounting of the project's results. In response, please provide evidence of benefit to focal fish populations. The work element descriptions are confusing and difficult to follow and understand. Identifying each subbasin plan relationship is distracting. The organization is not helpful. The ISRP suggests beginning this section by identifying in general terms what needs to happen in the next three years. Is more field inventory needed, and if so why? Is more analysis of the past inventory data needed, if so why? What are the priority areas and strategies for activities? Finally, what are the specific methods - in general terms - so they can be identified as appropriate and consistent with current scientific thinking? The proposal contains rather prescriptive declarations to implement BMPs (for example decommission 10 miles of road, fix one more mile or road, fix 2 barriers, fence 2 miles of stream, etc.). Yet in earlier work elements, there is considerable effort expended on more inventory, planning, and project design. How can it be at this juncture that the appropriate mix is 10 miles of road decommissioning and 2 miles of fence when the assessments are not yet complete? In response, please clarify the rationale for these prescriptions. The explanation of monitoring for compliance and effectiveness needs to be clarified. The effectiveness monitoring plan should be peer-reviewed during this funding cycle to ensure it is using the same methods and metrics recommended by PNAMP and CSMEP. At the local level of communicating with landowners and stakeholders the sponsors appear to perform admirably. In communicating with the extended scientific and management community, it appears there is room for much improvement. As an example, these proposals do not provide maps and summaries from the stream inventories, fish barrier assessment, and road analysis. Until a clearer picture of the amount of work and time needed to bring this watershed into a reasonable state of productivity is given, it is difficult to assess the likely benefits to the focal fish species. It is not possible to assess whether the restoration will take 10 or 200 years, given the information supplied in the proposal. The funding request appears to have increased significantly. What is the basis for that? Finally, in the response loop, the ISRP recommends that the Nez Perce Tribe suggest a priority and rank of the numerous proposals submitted under the titles “protect” and “restore.” Where do habitat actions and protection in the Clearwater offer the most potential benefit?
ISRP FINAL REVIEW (Aug 31, 2006)
Recommendation: Fundable in part
NPCC comments: This is an ISRP response to the fix it loop for proposal 199901700 Protect and Restore Lapwai Creek Watershed (NPT) and 200207000 Lapwai Creek Anadromous Habitat (NPSWCD) – integrated sister projects to address habitat restoration and protection on Lapwai Creek on tribal and private land, respectively. The sponsors addressed the questions raised by the ISRP in the preliminary review. The adequacy of the answers varied by question. The ISRP thanks the sponsors for the time and effort in producing the revised proposal narrative and explanations of the projects’ history. The ISRP had many questions for the sponsors, so the evaluation of the response to each is beyond the space and time available in this fix it loop review. Briefly, the proposal(s) were to execute tasks related to both inventory and assessment of fish populations and habitat, and habitat restoration implementation. From the proposal it was not clear to the ISRP how important to the focal species the watershed was; the focal species current status in the watershed; the role the watershed could contribute to the focal species’ status if restored; if the watershed could be restored; and how long it would take. Replies were provided to the ISRP’s questions and a revised narrative was produced. The answers to the questions and the narrative revision go a long way to clarifying for the ISRP the status and progress of anadromous fish species (primarily steelhead) and restoration potential in this watershed. Much more is needed however, before the ISRP can confidently assess whether the proposed activities in the Lapwai Creek system are scientifically sound, have quantifiable biological objectives that are measurable, and will benefit fish and wildlife (A-run steelhead). Sponsors indicate that it became apparent early in the project history (1999) that insufficient data existed to effectively address improving the status of anadromous fish in Lapwai Creek. Little was known about the status of the fish or the habitat. In the intervening period the sponsors state they have treated "hot spots" of habitat degradation, and nearly completed inventories of habitat conditions and fish population status. They report that inventory work will be completed in 2006 and that evaluation and analysis should be prepared in 2007. In the current revised narrative the biological objectives are tasks. The sponsors provide an ultimate goal: "to protect and restore the ecological and biological functions of the Lapwai Creek Watershed to assist in the recovery of anadromous and resident fish species," and this is reasonable. What is needed is a specific goal, with a timeframe for changes in habitat conditions and fish population abundance and productivity. Sponsors clarify for the ISRP their understanding of compliance and effectiveness monitoring, and inform the ISRP that they appreciate the necessity of effectiveness monitoring, but that it is beyond the willingness of Council and BPA to fund those data collections and analysis. The ISRP understands the constraints placed on sponsors, but also believes sponsors need to be creative in developing methods to determine whether their restoration efforts are providing a benefit. Can riparian habitat be evaluated by photopoints or aerial photography and be cost effective, how can stream flow and stream temperature be monitored? How can adult fish in and smolts out be measured? Sponsors indicate that stream habitat and watershed inventories, and fish population abundance will be completed soon and final assessments available in 2007. Based on that commitment, these projects are Fundable in Part (incrementally). In 2007, fundable only for completion of the inventory and assessments. Possibly fundable in 2008 and 2009 for restoration actions contingent upon a proposal narrative that uses those assessments to establish biological objectives, strategies and actions to get to those objectives, and an approach to measure whether progress is being made in achieving the objectives. For full comments on "restore and protect" type projects, please see heading “General comments concerning Nez Perce Tribe proposals to protect and restore various watersheds” at the beginning of the ISRP comments on project # 199607702, Protect & Restore Lolo Creek Watershed.