FY 2002 Columbia Plateau proposal 199506425
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
199506425 Narrative | Narrative |
Columbia Plateau: Yakima Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Columbia Plateau: Yakima Subbasin Map with BPA Fish & Wildlife Projects | Subbasin Map |
Section 1. Administrative
Proposal title | Policy/Technical Involvement and Planning in the Yakima/Klickitat Fisheries Project |
Proposal ID | 199506425 |
Organization | Washington Department of Fish & Wildlife (WDFW) |
Proposal contact person or principal investigator | |
Name | Todd Pearsons |
Mailing address | 600 Capitol Way North Olympia, WA 98501-1091 |
Phone / email | 5099254467 / [email protected] |
Manager authorizing this project | Bill Hopley |
Review cycle | Columbia Plateau |
Province / Subbasin | Columbia Plateau / Yakima |
Short description | Manage policy and technical oversight of the Yakima/Klickitat Fisheries Project via the project's Policy Group and Scientific and Technical Advisory Group as dilineated in the agreed-upon project management structure. |
Target species | Spring and fall chinook, coho, steelhead (listed as threatened in mid-Columbia ESU) |
Project location
Latitude | Longitude | Description |
---|---|---|
46.25 | -121.5 | These four points define a quadrant which encompasses the Yakima River Basin. Project activities are basin-wide. |
46.25 | -119 | These four points define a quadrant which encompasses the Yakima River Basin. Project activities are basin-wide. |
47.5 | -121.5 | These four points define a quadrant which encompasses the Yakima River Basin. Project activities are basin-wide. |
47.5 | -119 | These four points define a quadrant which encompasses the Yakima River Basin. Project activities are basin-wide. |
46.73 | -120.67 | Yakima subbasin |
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1987 | Draft Master Plan submitted as stipulated by the NPPC in the 1984 Fish and Wildlife Program. NPPC approves the Master Plan as "a reasonable basis upon which the BPA may proceed to fund predesign work" |
1990 | Preliminary Design Report resulting in conditional approval to proceed with the final design phase of the Yakima Production Project. |
1992 | Draft EIS issued presenting the "seven stock alternative" to supplement all salmon and steelhead stocks in the Yakima basic concurrently. |
1993 | Yakima/Klickitat Fisheries Project Planning Status Report, Volumes 1 through 5 completed. (spring chinook and coho revised 1995 and currently in revision) |
1995 | Biological Specifications Work Group completed two critical planning documents to guide design and operation of the Cle Elum Supplementation Research Facility. |
1996 | Final EIS issued. Preferred alternative to produce upper Yakima spring chinook juveniles at a hatchery facility to be located at Cle Elum, WA. The preferred alternative also included feasibility studies to test potential reintroduction of coho. |
1996 | Construction contract awarded for Cle Elum Supplementation Research Facility. |
1996 | Ground breaking ceremonies at Cle Elum, WA. |
1997 | First adult upper Yakima spring chinook are delivered to Cle Elum Supplementation Research Facility. |
1997 | Construction of main facility is complete. |
1998 | Second year of upper Yakima spring chinook brood stock collection for Cle Elum. |
1999 | First release of yearling upper Yakima spring chinook from acclimation sites. |
1999 | Third year of upper Yakima spring chinook brood stock collection for Cle Elum. |
2000 | Second release of yearling upper Yakima spring chinook from acclimation sites. |
2000 | Fourth year of upper Yakima spring chinook brood stock collection for Cle Elum. |
2000 | Completion of a controlled-flow spawning channel for reproductive success research. |
2000 | First introduction of wild spawning adult spring chinook to the controlled-flow channel and collection of emergent fry. |
2001 | Third release of yearling upper Yakima spring chinook from acclimation sites. |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
199701325 | YKFP Operations and Maintenance | Operation of the Cle Elum Supplementation and Research Facility |
199506325 | YKFP Monitoring and Evaluation | The major project providing the evaluation and information benefits from the YKFP. All Yakama Nation and WDFW M&E activities are contained in this project. |
198812025 | YKFP Management, Data and Habitat | The Yakama Nation project providing for project management oversight; equivalent to WDFW component proposed herein. |
198811525 | YKFP Design and Construction | Project construction including the Cle Elum hatchery, acclimation sites, and hatchery housing, etc. |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|---|---|---|---|
1. Provide POLICY coordination and management oversight of the Yakima/Klickitat Fisheries Project in cooperation with the Yakama Nation | a. Participate in and attend Policy Group meetings to develop Project policy and ensure implementation | ongoing | $28,175 | |
b. Within the YKFP Policy Group, assist in developing decisions and providing input to BPA to the extent those directions and decisions affect the implementation and outcome of the Project. | ongoing | $7,050 | ||
c. Within the YKFP Policy Group, manage the YKFP Adaptive Management cycle which includes participation in the Project Annual Review and review of Project Status Reports, the Uncertainty Resolution Plan, and recommendations brought forward by the STAC. | ongoing | $2,345 | ||
d. Within the YKFP Policy Group, assist in developing and pressenting information to the PPC as appropriate. | ongoing | $2,345 | ||
e. Within the YKFP Policy Group, facilitate refinement and maintenance of a YKFP project management structure. | ongoing | $2,345 | ||
f. Within the YKFP Policy Group, participate in developing budget allotments and contracting diractions. | ongoing | $2,345 | ||
g. Within the YKFP Policy Group, coordinate all environmental compliance (NEPA) activities related to the Project with BPA and YN. | ongoing | $2,345 | ||
2. Provide TECHNICAL and SCIENTIFIC Coordination of the Yakima/Klickitat Fisheries Project in cooperation with the Yakama Nation | a. Manage and direct all WDFW management, administrative, science and technical personnel participating in Project activities. | ongoing | $70,425 | |
b. Within the Scientific and Technical Advisory Committee (STAC), assist in management of standing and temporary committees assigned to STAC including the Monitoring Implementation Planning Team (MIPT). | ongoing | $35,225 | ||
c. Within the STAC, coordinate the adaptive management cycle: review and develop proposed amendments to the Project Status Report, and Uncertainty Resolution Plan and present to the Policy Group. | ongoing | $8,800 | ||
d. Attend Policy Group meetings and present technical recommendations, budget proposals, adaptive management amendments, or advice to the Policy Group as appropriate. | ongoing | $8,800 | ||
e. Attend STAC meetings and participate in review and coordination of all biologic aspects of the YKFP and the activities within the basin which affect the YKFP. | ongoing | $8,800 | ||
f. Within the STAC, assist in developing budget recommendations including allotments to accom plish tasks as approved by the Policy Group. | ongoing | $8,800 |
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|---|---|---|
1. Provide POLICY coordination and management oversight of the Yakima/Klickitat Fisheries Project in cooperation with the Yakama Nation. | 2003 | 2006 | $202,315 |
2. Provide TECHNICAL and SCIENTIFIC coordination of the Yakima/Klickitat Fisheries Project in cooperation with the Yakama Nation. | 2003 | 2006 | $606,945 |
Outyear budgets for Operations and Maintenance phase
FY 2003 | FY 2004 | FY 2005 | FY 2006 |
---|---|---|---|
$193,435 | $199,237 | $205,215 | $211,373 |
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2002 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2002 cost |
---|---|---|
Personnel | FTE: 1.8 (22 staff months) | $108,000 |
Fringe | $24,306 | |
Supplies | $10,204 | |
Travel | $7,490 | |
Indirect | $37,800 | |
$187,800 |
Total estimated budget
Total FY 2002 cost | $187,800 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2002 budget request | $187,800 |
FY 2002 forecast from 2001 | $267,800 |
% change from forecast | -29.9% |
Reason for change in estimated budget
Reduced staffing level, discontinued use of sub-contractor, and adjustments from expenditure experience.
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Fundable - no response required
Jun 15, 2001
Comment:
Fundable. The Washington Department of Fish and Wildlife (WDFW) and the Yakama Nation are co-managers of the YKFP. Project management is conducted through a policy group supported by a scientific and technical advisory committee. These joint groups are responsible for ensuring that all YKFP activities are implemented efficiently and effectively. This proposal describes WDFW participation in these co-manager responsibilities. The proposal is well organized and seems limited to the advisory role described in the text. The budget for FY02 is reduced from the forecasted level and remains very similar through FY06 (less than a 10% increase).
The failure of the planning effort to produce a solid experimental design reflects poorly on this project.
Comment:
CBFWA's review is consistent with the ISRP review and has been adequately addressed in the response to the ISRP for these projects. The Yakima Klickitat Fisheries Program (YKFP) is a collaborative, science-based resource management program. Funding of ongoing aspects should continue until complete.Comment:
Fundable. The Washington Department of Fish and Wildlife (WDFW) and the Yakama Nation are co-managers of the YKFP. Project management is conducted through a policy group supported by a scientific and technical advisory committee. These joint groups are responsible for ensuring that all YKFP activities are implemented efficiently and effectively. This proposal describes WDFW participation in these co-manager responsibilities. The proposal is well organized and seems limited to the advisory role described in the text. The budget for FY02 is reduced from the forecasted level and remains very similar through FY06 (less than a 10% increase).
The failure of the planning effort to produce a solid experimental design reflects poorly on this project.
See detailed ISRP comments on the YKFPs.
Comment:
Statement of Potential Biological Benefit to ESUN/A
Comments
Already ESA Req? N/A
Biop? no
Comment:
No cost-share. This project provides for the management of policy and technical oversight of the Yakima/Klickitat Fisheries Project via the project's Policy Group and Scientific and Technical Advisory Group as delineated in the agreed-upon project management structure. Need to identify potential redundancies (see YKFP comments above).Comment:
Comment:
Comment:
Indirect rate will possibly change.Comment:
NW Power and Conservation Council's FY 2006 Project Funding Review
expense
May 2005
FY05 NPCC start of year: | FY06 NPCC staff preliminary: | FY06 NPCC July draft start of year: |
$186,700 | $186,700 | $186,700 |
Sponsor comments: See comment at Council's website