Section 1. Administrative

Proposal titleMulti-Year Yakima Anadromous Fish Plan
Proposal ID20526
OrganizationColumbia Basin Fish & Wildlife Authority (CBFWA)
Proposal contact person or principal investigator
NameTom Giese
Mailing address2501 SW First Ave., Suite 200 Portland, OR 97201
Phone / email5032290191 / [email protected]
Manager authorizing this project
Review cycleFY 2000
Province / SubbasinColumbia Plateau / Yakima
Short description
Target species
Project location
LatitudeLongitudeDescription
Reasonable and Prudent Alternatives (RPAs)

Sponsor-reported:

RPA

Relevant RPAs based on NMFS/BPA review:

Reviewing agencyAction #BiOp AgencyDescription

Section 2. Past accomplishments

YearAccomplishment

Section 3. Relationships to other projects

Project IDTitleDescription
9100 Reopen blocked habitat.
9603301 Build incubation/rearing & 12 satellite facilities for adults/juveniles.
8811500 Planning, design, funding of facilities under #9603301.
9503300 O&M for production facilities.
9701300 O&M for production facilities.
9901200 Coordinate/Facilitate Watershed Project Planning/Implementation
9706200 Development & refinement of natural production objectives & strategies.
9603302 Evaluate potential risks of coho reintroductions.
9506300 Overall monitoring and evaluation.
8812005 Overall monitoring and evaluation.
9705100 Improve adult spawning habitat andjuvenile rearing/overwintering survival.
9506402 Research to examine interaction of salmonid species.
9506406 Improve supplementation fish.
8812001 Coordination, planning, use of new information to implement projects.
8506200 Ongoing evaluation of improved screens and ladders.
9105500 Improve supplementation fish.
9506404 Coordination, planning, use of new information to implement projects.
9067 Coordination, planning, use of new information to implement projects.
9405900 Educational outreach to gain regional support for Objective 1.
8812008 Identify limiting factors, make improvements to migration/prespawn survival
9102 Identify limiting factors, make improvements to migration/prespawn survival
9603501 Identify limiting factors, make improvements to migration/prespawn survival
9704900 Identify limiting factors, make improvements to migration/prespawn survival
9200900 O&M for completed improvments.
9105700 Completion of Phase I construction.
9107500 Completion of Phase I construction.
20526 MYP Yakima Anadromous Fish Plan
9101 Identify limiting factors, make improvements to migration/prespawn survival

Section 4. Budget for Planning and Design phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Planning and Design phase

Section 5. Budget for Construction and Implementation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Construction and Implementation phase

Section 6. Budget for Operations and Maintenance phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Operations and Maintenance phase

Section 7. Budget for Monitoring and Evaluation phase

Task-based budget
ObjectiveTaskDuration in FYsEstimated 2000 costSubcontractor
Outyear objectives-based budget
ObjectiveStarting FYEnding FYEstimated cost
Outyear budgets for Monitoring and Evaluation phase

Section 8. Estimated budget summary

Itemized budget
ItemNoteFY 2000 cost
Personnel $0
Fringe $0
Supplies $0
$0
Total estimated budget
Total FY 2000 cost$0
Amount anticipated from previously committed BPA funds$0
Total FY 2000 budget request$0
FY 2000 forecast from 1999$0
% change from forecast0.0%
Cost sharing
OrganizationItem or service providedAmountCash or in-kind

Reviews and recommendations

This information was not provided on the original proposals, but was generated during the review process.

Recommendation:
NA - Umbrella Proposal
Date:
Jun 15, 1999

Comment:

Recommendation: NA - Umbrella Proposal

Comments: This umbrella proposal was inadequate. It provides a short description of the Yakima Basin and some of the fishery problems existing there but no documentation or references. Many sections of the proposal are incomplete or not addressed. These include lists of critically dependent projects, past accomplishments, schedule constraints, completion dates, and budgets. The proposal does list the relationship of these projects to others in the basin in addressing these needs. Objective 1 seeks to restore "ecosystem integrity/function throughout all life history phases by implementing a "normative" or historical river ecosystem as an overall goal." Yet the only task under this objective involves increased enforcement and public awareness. Public awareness seems only a small part of what is needed to fulfill Objective 1.

It is unclear how all the actions to define limiting factors and make habitat improvements can be defined if a watershed assessment (e.g., Project #20118) has not been completed. The relationship among habitat work, planning, and production facilities under this umbrella to habitat projects in the Yakima Subbasin Habitat/Watershed Project Umbrella (#20547) is unclear. Are these various projects related or were they developed independently? Assuming they are coordinated at the subbasin level, how were priorities chosen? How will results from separate projects be integrated? How will effectiveness be monitored? This is not an adequate umbrella document. It is primarily a list of activities. The umbrella gives no clear description of the rationale, technical approach, or integration and sequencing of projects.


Recommendation:
Do Not Fund
Date:
Aug 20, 1999

Comment:


Recommendation:
Date:
Aug 20, 1999

Comment:

Criteria all: Met? NA -