FY 2000 proposal 20552
Contents
Section 1. General administrative information
Section 2. Past accomplishments
Section 3. Relationships to other projects
Section 4. Budgets for planning/design phase
Section 5. Budgets for construction/implementation phase
Section 6. Budgets for operations/maintenance phase
Section 7. Budgets for monitoring/evaluation phase
Section 8. Budget summary
Reviews and Recommendations
Additional documents
Title | Type |
---|---|
20552 Narrative | Narrative |
20552 Sponsor Response to the ISRP | Response |
Section 1. Administrative
Proposal title | Smolt Monitoring Program Umbrella |
Proposal ID | 20552 |
Organization | Pacific States Marine Fisheries Commission, Idaho Department of Fish & Wildlife, Nez Perce Tribe and USGS (PSMFC/IDFG/NP/USGS) |
Proposal contact person or principal investigator | |
Name | Michele Dehart |
Mailing address | 2501 SW First Ave., Suite 250 Portland, OR 97201 |
Phone / email | 5032304288 / [email protected] |
Manager authorizing this project | |
Review cycle | FY 2000 |
Province / Subbasin | Mainstem/Systemwide / Systemwide |
Short description | Juvenile salmonid migration monitoring for the Columbia and Snake rivers. |
Target species | chinook, steelhead, sockeye, coho |
Project location
Latitude | Longitude | Description |
---|
Reasonable and Prudent Alternatives (RPAs)
Sponsor-reported:
RPA |
---|
Relevant RPAs based on NMFS/BPA review:
Reviewing agency | Action # | BiOp Agency | Description |
---|
Section 2. Past accomplishments
Year | Accomplishment |
---|---|
1998 | successful implementation/distribution |
1997 | of data to the region |
1996 | |
1995 |
Section 3. Relationships to other projects
Project ID | Title | Description |
---|---|---|
9008000 | Columbia Basin Pit-Tag Information System | Dependent upon tag recapture data |
8712700 | Smolt Monitoring Program (Federal & Non-Federal dams) | |
8401400 | Smolt Monitoring Program - tagging | |
8712703 | Imnaha River Smolt Monitoring Program Project | |
20442 | Biological Monitoring Of Columbia River Basin Salmonids | |
940330 | The Fish Passage Center | |
8712702 | Comparative Survival Rate Study (CSS) Hatchery PIT tagged chinook | |
8332300 | Monitor Smolts at the Head of Lower Granite Reservoir & Lower Granite Dam | |
20552 | Smolt Monitoring Program | |
9602100 | Gas Bubble Disease Research & Monitoring of Juvenile Salmonids (one task) |
Section 4. Budget for Planning and Design phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Planning and Design phase
Section 5. Budget for Construction and Implementation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Construction and Implementation phase
Section 6. Budget for Operations and Maintenance phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Operations and Maintenance phase
Section 7. Budget for Monitoring and Evaluation phase
Task-based budget
Objective | Task | Duration in FYs | Estimated 2000 cost | Subcontractor |
---|
Outyear objectives-based budget
Objective | Starting FY | Ending FY | Estimated cost |
---|
Outyear budgets for Monitoring and Evaluation phase
Section 8. Estimated budget summary
Itemized budget
Item | Note | FY 2000 cost |
---|---|---|
Personnel | $0 | |
Fringe | $0 | |
Supplies | $0 | |
$0 |
Total estimated budget
Total FY 2000 cost | $0 |
Amount anticipated from previously committed BPA funds | $0 |
Total FY 2000 budget request | $0 |
FY 2000 forecast from 1999 | $0 |
% change from forecast | 0.0% |
Cost sharing
Organization | Item or service provided | Amount | Cash or in-kind |
---|
Other budget explanation
Schedule Constraints: None
Reviews and recommendations
This information was not provided on the original proposals, but was generated during the review process.
Comment:
Recommendation: NA - Umbrella ProposalComments: This proposal does not explain the goals and experimental design to reach the goals. With the way the umbrella and sub-proposals are set up it is not clear where the tags are being applied. The hardware is still not in place for adequate detection of adult returns. There is a critical need to install adult detection facilities, with multiple detection devices in each fish ladder.
Comment:
Comment:
Individual components reviewed below. These are critical and urgent priorities. Check integration of Project #8712703 Imnaha Smolt monitoring.Comment:
Criteria all: Met? NA -